What changed

Every change recorded in DCRA's weekly update, grouped by week and state. Each line comes from a reviewed record and links to its source. This is planning information, not a forecast.

Corrections and status changes are also listed in the corrections ledger. Machine-readable feed: changes.json.

Week of 2026-11-09 54 changes

Georgia

Added to the atlas
New information

Kansas

New information
Correction
  • 2026-11-14 Alcove Project Catalyst: Removed the repurposed city news URL from current citations: it now describes a separate 116-acre Northland exploration. Retained the 283-acre Catalyst announcement and existing stage. Previously: ks-catalyst-city-update cited as current Catalyst evidence. Source: City of Osawatomie and Alcove Development.

Kentucky

Permit / regulatory
Project status
New information

Louisiana

Project status
New information

Maryland

Permit / regulatory
New information
Correction
  • 2026-11-14 TeraWulf Morgantown: Clarified that the acquisition remains pending closing and regulatory approvals in the November issuer filing; an earlier regulatory authorization is not transaction closing. Previously: In development; generation described as acquired with the site. Source: TeraWulf Inc..

Ohio

New information
  • 2026-11-14 AWS Sidney: Added the city's statements that the facility will use the existing AES Ohio grid and that Amazon is modeling load impacts with AES Ohio and PJM. Source: City of Sidney.
  • 2026-11-14 Meta Piqua: Added a news report that plans call for AES Ohio to provide permanent service through a transmission connection, with 10 MW of temporary construction power. Source: Dayton Daily News.
  • 2026-11-14 PORTS-Pike Technology Campus: Added, as area context, AEP's siting application stating SB Energy's 9,200 MW request near Piketon and AEP Ohio's statement on who pays for the new 765 kV transmission. Source: AEP Ohio Transmission Company; AEP Ohio.

Texas

Added to the atlas
New information

Utah

Permit / regulatory
  • 2026-11-14 Stratos Project: KSL reports a new permanent water-use change application submitted October 15. Primary application details did not render; no water-right approval, actual use or reconciled generation capacity is inferred. Source: KSL. Public submission.
New information

Virginia

Added to the atlas
New information

Week of 2026-11-02 10 changes

Texas

New information

Week of 2026-10-26 12 changes

Georgia

Added to the atlas
  • 2026-10-28 Eatonton 379: Added to the atlas from a reviewed public project record.
  • 2026-10-28 Microsoft ATL80: Added from the October 20 DRI filing.

Kentucky

Added to the atlas
New information

Ohio

Added to the atlas

Texas

Project status
New information
Correction

Utah

Permit / regulatory

Week of 2026-10-12 12 changes

Kansas

Permit / regulatory
New information

Kentucky

New information

Louisiana

Project status
  • 2026-10-15 Hut 8 River Bend: October 5 on-site reporting describes active River Bend construction; stage changed from proposed to under construction at moderate confidence. Previously: Under development · lease signed Dec 2025; PROPOSED. Source: WAFB. Public submission.

Maryland

Permit / regulatory

Texas

Project status
New information

Utah

New information

Week of 2026-10-05 3 changes

Texas

New information
  • 2026-10-07 Hut 8 Beacon Point: In a follow-up, the ESD #1 chief wrote that cost recovery for an extended response has not been discussed (the district typically charges only for hazmat responses) and that the district has attended a multi-agency site-plan meeting for the construction phases, with more planned. Source: Nueces County Emergency Services District #1 (Annaville Fire Department).
  • 2026-10-06 Hut 8 Beacon Point: The Nueces County ESD #1 (Annaville) fire chief wrote that the district has fire jurisdiction of the area while the City of Corpus Christi Fire Marshal's Office reviews the fire code, including fire flow. Previously: Primary fire jurisdiction UNKNOWN. Source: Nueces County Emergency Services District #1 (Annaville Fire Department).
  • 2026-10-06 Hut 8 Beacon Point: The chief reported battery-fire training for responding crews, a pre-plan covering reignition monitoring, and mutual aid with the Corpus Christi Fire Department and the Refinery Terminal Fire Company (RTFC); runoff containment has not been addressed yet. Source: Nueces County Emergency Services District #1 (Annaville Fire Department).

Week of 2026-09-28 31 changes

Georgia

Added to the atlas
New information
Correction
  • 2026-09-30 OpenAI Project Camellia: Power supply relabeled as being contracted: OpenAI says it is contracting for 3.2 GW, not that a contract is signed. Previously: Contracted phased power delivery. Source: OpenAI.

Kansas

Added to the atlas

Kentucky

Project status

Ohio

Added to the atlas

Texas

Project status
Added to the atlas
New information
Correction
  • 2026-10-03 Hut 8 Beacon Point: Hut 8's representative reported on-site backup generation for the project; installation, type, fuel, and capacity remain unknown. Previously: Backup generation (type, fuel, capacity) UNKNOWN. Source: KRIS 6 News.

Utah

Added to the atlas

Virginia

Added to the atlas

Week of 2026-09-21 35 changes

Kentucky

Added to the atlas

Louisiana

Added to the atlas

Maryland

Added to the atlas

Ohio

Added to the atlas

Texas

Added to the atlas

Virginia

Added to the atlas