QTS Blakely
Data center campus proposal · Early County, GA
Status Permitting · concept stage VERIFIED · MODERATE Stage: Permitting / approvals
Last checked against its sources Sep 30, 2026
The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.
Profile
QTS proposes a data center campus in Blakely and says zoning, permits, environmental review, and utility agreements still govern the start date. QTS describes a potential 1,400 MW gross capacity at concept stage and a planned closed-loop cooling system with emergency generators. The capacity is a proposal, not current consumption or generation. VERIFIED · MODERATE
Key facts
- Potential gross campus capacity
- Potential 1,400 MW gross capacity
- VERIFIED · MODERATE
- Planned cooling design
- Closed-loop chilled-water system
- VERIFIED · MODERATE
- Planned emergency backup
- Diesel generators
- VERIFIED · MODERATE
- Primary fire jurisdiction / first-due agency
- Blakely Fire Department (named by QTS)
- VERIFIED · MODERATE
VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.
Open questions
- UNKNOWN The 1,400 MW concept has no cited final utility agreement or measured load.
- UNKNOWN Construction start, exact parcel, generator configuration, and water demand are unresolved.
- UNKNOWN QTS names the Blakely Fire Department as primary responder but does not establish its apparatus or specialized capabilities.
Changes (2)
- 2026-09-30 New information QTS Blakely: Added the primary fire department named by QTS (Blakely Fire Department). Source: QTS Data Centers.
- 2026-09-29 Added to the atlas QTS Blakely: Added to the atlas.
Sources (3)
- Blakely, Georgia Data Center Campus
- State of Georgia Counties - 2020 Census
- DCRA manual location approximation