Stratos Project
- Permitting / approvals
- Proposed hyperscale campus
- 16 sources
- Last checked Nov 14, 2026
Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Pre-construction; planning, entitlement and permitting underway
- Sourced · fair
- Reported water-rights application
- Permanent change application submitted October 15, 2026
- Calculated · fair
- Reconciled approved generation capacity
- Not in the public record
- Developer’s proposed on-site power
- Up to 2 GW Phase 1; approximately 7.5 GW long term
- Sourced · fair
- April 2026 private land in wider project area
- Approximately 40,000 acres
- Sourced · strong
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 2 terms used on this page
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- Closed-loop cooling
- A cooling system that recirculates the same water instead of drawing new water continuously.
Profile
Stratos remains in pre-construction in Box Elder County. The developer now describes an approximately 13,000-acre Utah campus, while MIDA’s wider project overview still uses approximately 40,000 acres. The Utah Senate confirmed scale-reduction commitments in June; these are not a surveyed boundary amendment. Current developer power plans differ from October reporting, so approved capacity and water-rights disposition remain unknown. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules
No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Backup generation
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Primary fire jurisdiction
- Not in the public record
Fire and rescue stations (11)
| Name | Straight-line distance | Role |
|---|---|---|
| Park Valley Fire Department | 19 mi NW | Potential mutual-aid origin |
| Snowville Fire Department | 30 mi NE | Potential mutual-aid origin |
| Alliant Techsystems Fire Station | 32 mi E | Potential mutual-aid origin |
| Thatcher Penrose Fire Department | 40 mi E | Potential mutual-aid origin |
| Grouse Creek Fire Department | 43 mi W | Potential mutual-aid origin |
| Tremonton Fire Department | 46 mi E | Potential mutual-aid origin |
| Garland Fire Department | 47 mi E | Potential mutual-aid origin |
| Portage Fire and Rescue Department | 49 mi ENE | Potential mutual-aid origin |
| Raft River Fire Protection District Station 2 | 49 mi N | Potential mutual-aid origin |
| Corinne Fire Department | 49 mi E | Potential mutual-aid origin |
Hospitals (1)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Bear River Valley Hospital | 46 mi E | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Approved data-center boundary, actual footprint, and exact point
- Facility draw, reconciled generation capacity, and physical gas-service route
- Primary water-rights application details, disposition, verified supply and actual water use
- Construction start, phase schedule, and response jurisdiction
Changes (4)
- 2026-11-14 Permit / regulatory Stratos Project: KSL reports a new permanent water-use change application submitted October 15. Primary application details did not render; no water-right approval, actual use or reconciled generation capacity is inferred. Source: KSL. Public submission.
- 2026-11-14 New information Stratos Project: Added the county's statement that the project will generate all its own power on site and take none from the local grid. Source: Box Elder County; Deseret News.
- 2026-10-15 New information Stratos Project: Developer describes pre-construction and an approximately 13,000-acre campus; retain April MIDA area as history, cite Senate concessions and distinguish conflicting generation plans. Grow the Flow is OWNER_REVIEWED only; revised water-rights filing remains unconfirmed. Source: O’Leary Digital; Military Installation Development Authority; Utah Senate; KSL; Business Insider; Box Elder County; Utah Clean Energy; Wikipedia; Grow the Flow. Public submission.
- 2026-10-04 Added to the atlas Stratos Project: Added to the atlas.
Related data centers
Others in Utah
Cite this record
"Stratos Project", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/stratos-box-elder, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.