Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Operational
- Sourced · strong
- Power infrastructure capacity
- 80 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). power capacity
- Sourced · fair
- Building area
- 200,000 sq ft carrier hotel
- Sourced · fair
- Backup generation
- Not in the public record
- Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
- Not in the public record
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 3 terms used on this page
- Interconnection agreement
- The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for.
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- UPS (uninterruptible power supply)
- Batteries that keep computers running through the seconds between a power loss and backup generators starting.
Profile
One Market Center at 300 West Lexington Street is a major carrier hotel and enterprise colocation data center in downtown Baltimore, Maryland. Operated by AiNET, the 200,000-square-foot facility features up to 80 MW of utility electrical infrastructure capacity served by BGE within PJM. It serves as a primary telecommunications Interconnection agreement: The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for. and cloud peering hub in the Baltimore metropolitan area. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules · PJM
No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Battery / UPS system
- Not in the public record
- Backup generation
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Fire jurisdiction
- Baltimore City Fire Department (NERIS boundary)
- Calculated · weak
- Jurisdiction department type
- Career
- Sourced · fair
- Department staffing
- 1,625 career full-time · 0 volunteer firefighters
- Sourced · fair
- Department stations
- 41 stations
- Sourced · fair
- Services the department lists
- Not in the public record
Fire and rescue stations (518)
| Name | Straight-line distance | Role |
|---|---|---|
| Baltimore City Fire Station 23 | 0.3 mi S | Nearby origin |
| Thomas J Burke Fire Station | 0.9 mi ENE | Nearby origin |
| Baltimore City Fire Station 33 | 0.9 mi SSE | Nearby origin |
| Baltimore City Fire Station 22 | 1.1 mi NNW | Nearby origin |
| Baltimore City Fire Station 34 | 1.2 mi SSE | Nearby origin |
| Baltimore City Fire Station 8 | 1.3 mi WNW | Nearby origin |
| Baltimore City Fire Station 32 | 1.3 mi SW | Nearby origin |
| Baltimore City Fire Station 18 | 1.5 mi WSW | Nearby origin |
| Baltimore City Fire Station 19 | 1.8 mi W | Nearby origin |
| Baltimore City Fire Station 35 | 1.8 mi SE | Nearby origin |
Hospitals (86)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Baltimore Veteran Affairs Medical Center | 0.3 mi WSW | Not in the public record |
| University of Maryland Medical Center | 0.4 mi SW | Not in the public record |
| Mercy Medical Center | 0.4 mi ENE | Not in the public record |
| University of Maryland Medical Center Midtown Campus | 0.6 mi N | Not in the public record |
| Kennedy Krieger Institute | 1.5 mi ENE | Not in the public record |
| Johns Hopkins Hospital | 1.5 mi ENE | Not in the public record |
| Grace Medical Center | 1.6 mi W | Not in the public record |
| Medstar Union Memorial Hospital | 2.6 mi N | Not in the public record |
| Medstar Harbor Hospital | 2.8 mi S | Not in the public record |
| Ascension Saint Agnes Hospital | 3.1 mi WSW | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Active power draw vs total installed capacity
- Diesel backup generator storage volume and air quality permits
- UPS battery chemistry and fire suppression systems
Changes (1)
- 2026-09-26 Added to the atlas AiNET One Market Center: Added to the atlas.
Related data centers
Others in Maryland
Cite this record
"AiNET One Market Center", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/ainet-one-market-center, last checked Sep 26, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.