Vantage OH1 New Albany

Hyperscale data center campus · Licking County, OH

Vantage Data Centers

Status Under development; current operating phase UNKNOWN VERIFIED · MODERATE Stage: Under construction
Last checked against its sources Sep 27, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

Vantage broke ground on its New Albany OH1 campus in October 2024. It describes a 70-acre, three-building plan with 192 MW of critical IT load and names AEP Ohio as power provider. The 192 MW is a planned IT design figure, not the campus's utility draw capacity; completion of the first phase remains unverified here. VERIFIED · MODERATE

Key facts

Planned campus area
70 acres
VERIFIED · MODERATE
Planned critical IT load
192 MW critical IT load at full buildout
VERIFIED · MODERATE
Planned cooling system
Closed-loop chilled water using air-cooled chillers
VERIFIED · MODERATE
Facility electrical draw capacity (MW)
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (5)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.