TeraWulf Muskie Data Campus

Proposed data center campus · Boyd County, KY

TeraWulf Inc.

Status Expanded electric-service agreement pending PSC approval VERIFIED · MODERATE Stage: Permitting / approvals
Last checked against its sources Oct 28, 2026

Open in the interactive atlas →

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

TeraWulf is developing Muskie at EastPark in eastern Kentucky. Its amended Kentucky Power agreement would increase contracted demand from 500 MW to 1 GW, with phases planned for 2028 and 2029, subject to PSC approval and utility construction. The Boyd County marker is regional context near the Greenup border; it is not a campus boundary. VERIFIED · MODERATE

Key facts

Amended utility power plan
1 GW, subject to regulatory approval
VERIFIED · MODERATE
Planned power ramp
First 500 MW in 2028; second 500 MW in 2029
VERIFIED · MODERATE
Named utility in pending agreement
Kentucky Power (AEP)
VERIFIED · MODERATE
Secured facility electrical draw capacity
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (5)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.