Status Operational since Aug 2020 VERIFIED · MODERATE Stage: In service
Last checked against its sources Sep 25, 2026

Open in the interactive atlas →

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

Meta's Henrico data center in White Oak Technology Park began serving traffic in August 2020. It was announced in 2017 as a 970,000 ft², $750 million project on 300 acres and has grown to five buildings and more than 2.4 million ft². Meta reports contracting more than 500 MW of new Virginia solar to match its use. VERIFIED · MODERATE

Key facts

Floor area
2.4M+ ft² · 5 buildings
VERIFIED · MODERATE
Initial project (2017)
970,000 ft² on a 300-acre site; $750M
VERIFIED · HIGH
Contracted new solar
500+ MW (Virginia)
VERIFIED · MODERATE
Power capacity (MW)
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.