Meta Temple Data Center

Meta Platforms, Inc. · Bell County, Texas

Open in the interactive atlas →Company project page ↗

Key facts

Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.

What the labels mean
Sourced
A cited source states it. Open the source to see who said it.
Calculated
DCRA calculated it from sourced values. The math is shown.
Estimate
An approximation where no source states the value.
Modeled
Output of an illustrative planning scenario. Not a forecast.
Unknown
Not in the public record. Unknown, not absent.
Sourced · strong
Strong: read directly in a primary record, such as a filing or the company's own release.
Sourced · fair
Fair: a company statement of its own plans, an official's written reply, or a solid report.
Sourced · weak
Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.

The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.

Status
Operational · online July 2026
Sourced · strong
Building area
760,000+ ft² (2 buildings)
Sourced · strong
Announced investment
>$1.2 billion
Sourced · strong
Site area
393 acres (2022 city figure)
Sourced · fair
Electric utility
Oncor (company)
Sourced · fair

"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.

Plain-language glossary: 3 terms used on this page
PUCT (Public Utility Commission of Texas)
The state agency that regulates electric utilities, including the rules for who pays for grid equipment.
MW (megawatt)
A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
UPS (uninterruptible power supply)
Batteries that keep computers running through the seconds between a power loss and backup generators starting.

Profile

Meta's Temple data center began serving traffic in July 2026. It has more than 760,000 ft² in two buildings and more than $1.2 billion of investment, and Meta calls it its first AI-optimized data center to come online. Meta says it planned the site's energy supply with Oncor Electric. Sourced · fair

Power and the grid

What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.

Loading grid records…

Published grid documents and the capacity comparison are in the interactive atlas, under Energy.

Who pays for the grid equipment

Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.

Filed grid projects

No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.

Who pays for this facility's connection

Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.

The rules

No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.

Hazards

Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.

What this facility's record says

Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
Not in the public record
Backup generation
Not in the public record

Emergency response

The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.

Fire jurisdiction

Primary fire jurisdiction
Not in the public record

Fire and rescue stations (151)

NameStraight-line distanceRole
Temple Fire and Rescue Station 8
Temple Fire & Rescue
0.6 mi WNearby origin
Temple Fire and Rescue Station 7
Temple Fire & Rescue
2.4 mi SWNearby origin
Temple Fire and Rescue Station 5
Temple Fire & Rescue
2.5 mi SENearby origin
Temple Fire and Rescue Station 6
Temple Fire & Rescue
3.1 mi ENearby origin
Morgan's Point Resort Volunteer Fire Department
Morgan's Point Resort Fire Department
3.3 mi WNearby origin
Temple Fire and Rescue Station 1
Temple Fire & Rescue
4.4 mi SENearby origin
Temple Fire and Rescue Station 3
Temple Fire & Rescue
4.4 mi SNearby origin
Moffat Volunteer Fire Department5.0 mi NWNearby origin
Belton Fire Department Station 2
Belton Fire Department
5.6 mi SWNearby origin
Temple Fire and Rescue Station 2
Temple Fire & Rescue
5.8 mi SENearby origin

The nearest 10 of 151. See all of them in the atlas →

Hospitals (23)

NameStraight-line distanceEmergency department
Baylor Scott and White Continuing Care Hospital - Temple1.5 mi SNot in the public record
Baylor Scott and White Medical Center - Temple4.8 mi SSENot in the public record
Baylor Scott and White McLane Children's Medical Center - Temple4.9 mi SSENot in the public record
Olin E Teague Veterans Affairs Medical Center5.3 mi SENot in the public record
Temple Rehabilitation Hospital5.8 mi SSENot in the public record
Cedar Crest Hospital and Residential Treatment Center9.4 mi SSWNot in the public record
Carl R Darnall Army Medical Center22 mi WNot in the public record
AdventHealth Central Texas Hospital24 mi WNot in the public record
Hillcrest Medical Center28 mi NNENot in the public record
Ascension Providence Hospital28 mi NNENot in the public record

The nearest 10 of 23. See all of them in the atlas →

Distances: Calculated · weak

Sources for these stations and hospitals (2)

What this record is missing

No public source yet for:

  • Power capacity ( (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).)
  • Cooling method and water use (the city's 4,000 gal/day cap applies to a different project)
  • Local response resources not yet recorded

Changes (2)

Related data centers

More from Meta Platforms, Inc.

Others in Texas

Cite this record

"Meta Temple Data Center", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/meta-temple, last checked Sep 24, 2026. Licensed under CC BY-NC 4.0.

Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.