Digital Realty Astra Enterprise Park
- Permitting / approvals
- Hyperscale data center campus
- 6 sources
- Last checked Nov 14, 2026
Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Permitting · development review
- Sourced · fair
- Proposed household credits
- Up to $1,000 annually for ten years
- Sourced · fair
- Proposed Astra North floor area
- Approximately 3 million ft²
- Sourced · fair
- Announced utility power delivery
- 600 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). by early 2028; up to 2 GW full delivery
- Sourced · fair
- Proposed Astra North phase area
- 280 acres
- Sourced · fair
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 1 terms used on this page
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
Profile
Digital Realty acquired land at Astra Enterprise Park for hyperscale development and announced an energy-service agreement for 600 MW of utility power by early 2028, rising to 2 GW at full delivery. The City of De Soto describes the proposal as in development review. Current city and developer pages describe Astra North as about 280 acres, nine buildings and about 3 million square feet. The October 9 company release commits $20 million toward household relief, with credit terms still being finalized. Announced utility-power capacity is not measured facility load. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules
No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Backup generation details
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Fire jurisdiction
- Not in the public record
Fire and rescue stations (306)
| Name | Straight-line distance | Role |
|---|---|---|
| Northwest Consolidated Fire District Station 13 | 0.4 mi NW | Nearby origin |
| De Soto Fire and Rescue Department Station 2 | 1.1 mi NW | Nearby origin |
| Northwest Consolidated Fire District Station 11 | 1.7 mi SSE | Nearby origin |
| Sherman Township Fire Department | 3.4 mi N | Nearby origin |
| Sherman Township Fire and Rescue Station 2 | 4.5 mi WNW | Nearby origin |
| Northwest Consolidated Fire District Station 12 | 5.5 mi SSE | Nearby origin |
| Lenexa Fire Department Station 3 | 5.5 mi E | Nearby origin |
| Olathe Fire Department Station 6 | 6.1 mi ESE | Nearby origin |
| Shawnee Fire Department Station 73 | 6.2 mi ENE | Nearby origin |
| Fairmount Township Fire Department Station 2 | 6.9 mi N | Nearby origin |
Hospitals (51)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| AdventHealth Prairie Star | 5.9 mi ESE | Not in the public record |
| Olathe Medical Center | 11 mi SE | Not in the public record |
| Meadowbrook Rehabilitation Hospital | 11 mi S | Not in the public record |
| Overland Park Regional Medical Center | 13 mi E | Not in the public record |
| Providence Medical Center | 14 mi NE | Not in the public record |
| Shawnee Mission Medical Center | 15 mi E | Not in the public record |
| Lawrence Memorial Hospital | 15 mi W | Not in the public record |
| Saint Luke's South Hospital | 17 mi ESE | Not in the public record |
| Children's Mercy Hospital Kansas | 17 mi E | Not in the public record |
| Heartland Surgical Specialty Hospital | 17 mi E | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Final phase design and approvals remain open; the current city and developer pages describe 280 acres and nine buildings for Astra North.
- The announcement names a local utility but does not name it; city materials separately report coordination with Evergy, which is not treated as a confirmed service agreement.
- Measured load, detailed cooling and water use, backup generation, and construction start remain unknown.
Changes (3)
- 2026-11-14 New information Digital Realty Astra Enterprise Park: Added the city's account of Digital Realty's statements that it will fund the electric infrastructure the project needs and use generators only for emergencies and testing. Source: City of De Soto, Kansas.
- 2026-10-15 New information Digital Realty Astra Enterprise Park: Current city and developer pages support Astra North’s proposed 280 acres, nine buildings and approximately 3 million square feet, replacing earlier UNKNOWN phase fields; company announces household-credit commitment with terms not yet final. Source: Digital Realty; Digital Realty; City of De Soto, Kansas. Public submission.
- 2026-09-28 Added to the atlas Digital Realty Astra Enterprise Park: Added to the atlas.
Related data centers
Others in Kansas
Cite this record
"Digital Realty Astra Enterprise Park", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/digital-realty-astra-de-soto, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.