Digital Realty Astra Enterprise Park
Hyperscale data center campus · Johnson County, KS
Status Permitting · development review VERIFIED · MODERATE Stage: Permitting / approvals
Last checked against its sources Sep 28, 2026
The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.
Profile
Digital Realty acquired land at Astra Enterprise Park for hyperscale development and announced an energy-service agreement for 600 MW of utility power by early 2028, rising to 2 GW at full delivery. The City of De Soto describes the proposal as in development review. A September 2026 local-news preview reports a change to phase plans, but no revised primary record was found, so current phase acreage and building count remain unknown. Announced utility-power capacity is not measured facility load. VERIFIED · MODERATE
Key facts
- Announced utility power delivery
- 600 MW by early 2028; up to 2 GW full delivery
- VERIFIED · MODERATE
- Current phase acreage
- UNKNOWN
- UNKNOWN · UNKNOWN
- Current phase building count
- UNKNOWN
- UNKNOWN · UNKNOWN
- Backup generation details
- UNKNOWN
- UNKNOWN · UNKNOWN
VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.
Open questions
- UNKNOWN The city page's earlier phase acreage and building count may have changed after a customer cancellation reported on September 23; no updated primary record was located.
- UNKNOWN The announcement names a local utility but does not name it; city materials separately report coordination with Evergy, which is not treated as a confirmed service agreement.
- UNKNOWN Measured load, detailed cooling and water use, backup generation, and construction start remain unknown.
Changes (1)
- 2026-09-28 Added to the atlas Digital Realty Astra Enterprise Park: Added to the atlas.