DC BLOX Atlanta West

DC BLOX · Douglas County, Georgia

Open in the interactive atlas →Company project page ↗

Key facts

Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.

What the labels mean
Sourced
A cited source states it. Open the source to see who said it.
Calculated
DCRA calculated it from sourced values. The math is shown.
Estimate
An approximation where no source states the value.
Modeled
Output of an illustrative planning scenario. Not a forecast.
Unknown
Not in the public record. Unknown, not absent.
Sourced · strong
Strong: read directly in a primary record, such as a filing or the company's own release.
Sourced · fair
Fair: a company statement of its own plans, an official's written reply, or a solid report.
Sourced · weak
Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.

The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.

Status
Partly in service · expansion open
Sourced · fair
Campus acreage
Not in the public record
Committed and planned critical IT capacity
200 critical (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
Sourced · fair
Whole-campus utility power capacity (MW)
Not in the public record
Backup generation
Not in the public record

"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.

Plain-language glossary: 1 terms used on this page
MW (megawatt)
A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).

Profile

DC BLOX markets Atlanta West in Douglas County as a hyperscale campus with operational and developing capacity. It reports one remaining 80 MW critical IT building available and GreyStone Power Cooperative as utility provider. The published critical IT figures do not establish whole-campus facility electrical draw, and the company's differing acreage descriptions leave current site area unknown. Sourced · fair

Power and the grid

What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.

Loading grid records…

Published grid documents and the capacity comparison are in the interactive atlas, under Energy.

Who pays for the grid equipment

Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.

Filed grid projects

No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.

Who pays for this facility's connection

Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.

The rules

No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.

Hazards

Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.

What this facility's record says

Backup generation
Not in the public record

Emergency response

The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.

Fire jurisdiction

Fire jurisdiction
Not in the public record

Fire and rescue stations (463)

NameStraight-line distanceRole
Douglas County Fire Department Station 5
Douglas County Fire Department
2.9 mi ENearby origin
Douglas County Fire Department Station 3
Douglas County Fire Department
3.4 mi SWNearby origin
Douglas County Fire Department Station 10
Douglas County Fire Department
3.4 mi NNENearby origin
Douglas County Fire/EMS Department Station 2
Douglas County Fire Department
3.8 mi WNWNearby origin
Douglas County Fire Department Station 11
Douglas County Fire Department
4.7 mi NNENearby origin
Douglas County Fire Department Station 76.1 mi NNENearby origin
Douglas County Fire Department Station 8
Douglas County Fire Department
6.8 mi WNWNearby origin
Douglas County Fire Department Station 6
Douglas County Fire Department
6.8 mi ENearby origin
Douglas County Fire Department Station 4 Fairplay
Douglas County Fire Department
7.4 mi SWNearby origin
South Fulton Fire and Rescue Department Station 8
City Of South Fulton Fire And Rescue Department
7.9 mi SENearby origin

The nearest 10 of 463. See all of them in the atlas →

Hospitals (59)

NameStraight-line distanceEmergency department
Youth Villages Inner Harbor Campus2.5 mi SENot in the public record
Wellstar Douglas Hospital3.3 mi NENot in the public record
Tanner Medical Center Villa Rica Campus9.1 mi WNWNot in the public record
Wellstar Paulding Hospital14 mi NNot in the public record
Wellstar Cobb Hospital14 mi NENot in the public record
Ridgeview Institute Hospital18 mi NENot in the public record
Anchor Hospital19 mi ESENot in the public record
Wellstar Atlanta Medical Center South20 mi ENot in the public record
Tanner Medical Center Carrollton Campus20 mi WSWNot in the public record
Wellstar Windy Hill Hospital21 mi NENot in the public record

The nearest 10 of 59. See all of them in the atlas →

Distances: Calculated · weak

Sources for these stations and hospitals (2)

What this record is missing

No public source yet for:

  • Whole-campus utility draw and measured consumption are not established by the critical IT figure.
  • Current campus acreage is unclear because two descriptions on the cited company page differ.
  • Backup generation, water demand, and individual building in-service dates are unknown.

Changes (2)

Related data centers

Others in Georgia

Cite this record

"DC BLOX Atlanta West", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/dcblox-atlanta-west-ga, last checked Sep 29, 2026. Licensed under CC BY-NC 4.0.

Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.