Corrections ledger
When DCRA corrects a value, or a project's status changes, the change is recorded here with its date, what the record said before, and the source for the new value. Nothing is edited out quietly.
Anyone can ask for a value to be checked. Each request needs a source, and a person reviews it against that source before anything changes. Accepted changes are listed here and link to their public submission.
- 2026-10-03 Project status Hut 8 Beacon Point: Corrected the stage to under construction: Hut 8's July release says construction had commenced. Previously: Under development · fully leased; PERMITTING. Source: Hut 8 Corp. (via PR Newswire).
- 2026-10-03 Correction Hut 8 Beacon Point: Hut 8's representative reported on-site backup generation for the project; installation, type, fuel, and capacity remain unknown. Previously: Backup generation (type, fuel, capacity) UNKNOWN. Source: KRIS 6 News.
- 2026-09-30 Correction OpenAI Project Camellia: Power supply relabeled as being contracted: OpenAI says it is contracting for 3.2 GW, not that a contract is signed. Previously: Contracted phased power delivery. Source: OpenAI.
- 2026-09-30 Project status PowerHouse Louisville: Independent local reports describe construction activity at the campus. Previously: In development. Source: The Louisville Cardinal; Spectrum News 1.