Corrections ledger
When DCRA corrects a value, or a project's status changes, the change is recorded here with its date, what the record said before, and the source for the new value. Nothing is edited out quietly.
Anyone can ask for a value to be checked. Each request needs a source, and a person reviews it against that source before anything changes. Accepted changes are listed here and link to their public submission.
- 2026-11-14 Correction Alcove Project Catalyst: Removed the repurposed city news URL from current citations: it now describes a separate 116-acre Northland exploration. Retained the 283-acre Catalyst announcement and existing stage. Previously: ks-catalyst-city-update cited as current Catalyst evidence. Source: City of Osawatomie and Alcove Development.
- 2026-11-14 Project status TeraWulf Justified Data: November issuer filing explicitly reports campus-wide construction underway; approved service is reported at 482 MW, with delivery targeted for late 2027 through Q2 2028. Google credit support and Fluor EPC agreements are recorded. Previously: Development; PROPOSED; 480 MW gross availability in the earlier company announcement. Source: TeraWulf Inc.; TeraWulf Inc. / U.S. Securities and Exchange Commission. Public submission.
- 2026-11-14 Project status Amazon Northwest Louisiana: Recorded reported Shreveport special-use permit appeal within the three-campus program; latest court disposition and building construction remain unconfirmed. Previously: Announced / planned; PROPOSED. Source: KTAL/KMSS via AOL. Public submission.
- 2026-11-14 Correction TeraWulf Morgantown: Clarified that the acquisition remains pending closing and regulatory approvals in the November issuer filing; an earlier regulatory authorization is not transaction closing. Previously: In development; generation described as acquired with the site. Source: TeraWulf Inc..
- 2026-10-28 Project status Fermi America HyperGrid (Project Matador): Company explicitly reports campus construction progress; stage changed to UNDER_CONSTRUCTION. No data-hall delivery or nuclear operating authorization established. Previously: Power campus in development; nuclear combined-license review pending; PERMITTING. Source: Fermi America; U.S. Nuclear Regulatory Commission / Federal Register. Public submission.
- 2026-10-28 Correction Fermi America HyperGrid (Project Matador): Current company campus scope is approximately 8,400 acres, replacing the earlier 5,800-acre announcement; not a surveyed boundary. Previously: 5,800 acres planned. Source: Fermi America. Public submission.
- 2026-10-28 Correction Hut 8 Beacon Point: Removed the sourced prevailing-wind default: the cited NWS page studies selected severe-wind events and does not establish prevailing wind climatology. Local prevailing wind is UNKNOWN; scenario wind remains an illustrative input. Previously: 135 degrees; NWS Corpus Christi prevailing SE. Source: National Weather Service, Corpus Christi (CRP).
- 2026-10-15 Project status Hut 8 River Bend: October 5 on-site reporting describes active River Bend construction; stage changed from proposed to under construction at moderate confidence. Previously: Under development · lease signed Dec 2025; PROPOSED. Source: WAFB. Public submission.
- 2026-10-15 Project status Fermi America HyperGrid (Project Matador): NRC draft EIS establishes pending combined-license review for four proposed nuclear units; campus stage changed to permitting, without asserting data-hall construction. Previously: Early development; PROPOSED. Source: U.S. Nuclear Regulatory Commission / Federal Register.
- 2026-10-15 Project status Stargate Milam County (SB Energy): SB Energy now identifies Milam as under construction; current capacity scope remains unresolved against the earlier 1,200 MW announcement. Previously: Under development · Phase 1 filed with TDLR; PERMITTING. Source: SB Energy; Texas Economic Development Corporation. Public submission.
- 2026-10-03 Project status Hut 8 Beacon Point: Corrected the stage to under construction: Hut 8's July release says construction had commenced. Previously: Under development · fully leased; PERMITTING. Source: Hut 8 Corp. (via PR Newswire).
- 2026-10-03 Correction Hut 8 Beacon Point: Hut 8's representative reported on-site backup generation for the project; installation, type, fuel, and capacity remain unknown. Previously: Backup generation (type, fuel, capacity) UNKNOWN. Source: KRIS 6 News.
- 2026-09-30 Correction OpenAI Project Camellia: Power supply relabeled as being contracted: OpenAI says it is contracting for 3.2 GW, not that a contract is signed. Previously: Contracted phased power delivery. Source: OpenAI.
- 2026-09-30 Project status PowerHouse Louisville: Independent local reports describe construction activity at the campus. Previously: In development. Source: The Louisville Cardinal; Spectrum News 1.