AWS New Albany

Amazon Web Services · Licking County, Ohio

Open in the interactive atlas →

Key facts

Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.

What the labels mean
Sourced
A cited source states it. Open the source to see who said it.
Calculated
DCRA calculated it from sourced values. The math is shown.
Estimate
An approximation where no source states the value.
Modeled
Output of an illustrative planning scenario. Not a forecast.
Unknown
Not in the public record. Unknown, not absent.
Sourced · strong
Strong: read directly in a primary record, such as a filing or the company's own release.
Sourced · fair
Fair: a company statement of its own plans, an official's written reply, or a solid report.
Sourced · weak
Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.

The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.

Status
Partly operational; expansion under construction
Sourced · strong
AWS Licking County investment, 2015–2024
$6.2 billion across county infrastructure
Sourced · strong
Newest campus phase, August 2025
Two buildings completed and staffed; remaining facilities under construction
Sourced · strong
Facility electrical draw capacity ( (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).)
Not in the public record
Confirmed serving utility
Not in the public record

"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.

Plain-language glossary: 2 terms used on this page
MW (megawatt)
A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
UPS (uninterruptible power supply)
Batteries that keep computers running through the seconds between a power loss and backup generators starting.

Profile

AWS has data-center infrastructure in Licking County. In August 2025, the City of New Albany reported that two buildings at its newest campus were constructed and staffed while others remained under construction. The city's $6.2 billion figure covers AWS investment across Licking County from 2015 through 2024, not this campus alone. Sourced · strong

Power and the grid

What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.

Loading grid records…

Published grid documents and the capacity comparison are in the interactive atlas, under Energy.

Who pays for the grid equipment

Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.

Filed grid projects

No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.

Who pays for this facility's connection

Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.

The rules

No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.

Hazards

Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.

What this facility's record says

Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
Not in the public record
Backup generation
Not in the public record

Emergency response

The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.

Fire jurisdiction

Fire jurisdiction
Monroe Township Fire Department (NERIS boundary)
Calculated · weak
Jurisdiction department type
Combination
Sourced · fair
Department staffing
11 career full-time · 29 volunteer firefighters
Sourced · fair
Department stations
2 stations
Sourced · fair
Services the department lists
Not in the public record

Fire and rescue stations (275)

NameStraight-line distanceRole
Plain Township Fire Department3.1 mi WSWNearby origin
Monroe Township Fire Department - Station 5015.3 mi NENearby origin
Harlem Township Division of Fire Station 450
Harlem Township Division Of Fire
5.7 mi NWNearby origin
Jefferson Township Fire Department6.5 mi SWNearby origin
Saint Albans Township Fire Department
St. Albans Township Fire Department
7.0 mi ENearby origin
Mifflin Township Fire Station 133
Mifflin Township - Division Of Fire
7.1 mi WSWNearby origin
Columbus Division of Fire Station 29
Columbus Division Of Fire
7.2 mi WNearby origin
West Licking Joint Fire District Station 3
West Licking Joint Fire District
7.5 mi SNearby origin
West Licking Joint Fire District Station 1
West Licking Joint Fire District
7.9 mi SENearby origin
Westerville Division of Fire Station 112
Westerville Division Of Fire
8.3 mi WNearby origin

The nearest 10 of 275. See all of them in the atlas →

Hospitals (48)

NameStraight-line distanceEmergency department
Mount Carmel New Albany Surgical Hospital2.5 mi WSWNot in the public record
Mount Carmel East Hospital9.7 mi SSWNot in the public record
Columbus Springs East Hospital11 mi WSWNot in the public record
Mount Carmel Saint Ann's Hospital11 mi WNot in the public record
OhioHealth Westerville Medical Center11 mi WNWNot in the public record
Mount Carmel Rehabilitation Hospital11 mi WNWNot in the public record
OhioHealth Pickerington Methodist Hospital13 mi SNot in the public record
Mount Carmel Behavioral Health Hospital13 mi SSWNot in the public record
SUN Behavioral Health-Columbus13 mi WNot in the public record
The Ohio State University Hospitals East14 mi SWNot in the public record

The nearest 10 of 48. See all of them in the atlas →

Distances: Calculated · weak

Sources for these stations and hospitals (2)

What this record is missing

No public source yet for:

  • Current phase completion and exact campus footprint
  • Facility electrical draw capacity and serving utility
  • Backup generation, batteries, cooling, and water use
  • Primary fire jurisdiction and response capabilities

Changes (1)

Related data centers

More from Amazon Web Services

Others in Ohio

Cite this record

"AWS New Albany", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/aws-new-albany-oh, last checked Sep 27, 2026. Licensed under CC BY-NC 4.0.

Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.