Eatonton 379
Proposed data center campus · Putnam County, GA
Status DRI review filing; local approvals unresolved VERIFIED · MODERATE Stage: Permitting / approvals
Last checked against its sources Oct 28, 2026
The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.
Profile
Putnam County submitted DRI 4861 for Eatonton 379, a proposed approximately 543-acre, eleven-building data-center development. The filing estimates approximately 520 MW of peak connected electrical load and names two alternative energy suppliers. Local approvals, secured service and construction are unresolved; inconsistent floor-area fields are not reconciled. VERIFIED · MODERATE
Key facts
- Proposed site area
- Approximately 543 acres
- VERIFIED · MODERATE
- Proposed buildings
- 11
- VERIFIED · MODERATE
- Filing estimate of peak connected electrical load
- Approximately 520 MW estimated peak connected load
- ESTIMATED · MODERATE
- Secured facility electrical draw capacity
- UNKNOWN
- UNKNOWN · UNKNOWN
VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.
Open questions
- UNKNOWN Surveyed campus boundary and parcel-level location
- UNKNOWN Confirmed electric service, measured load and completed phases
- UNKNOWN Backup generation, actual water use and primary fire jurisdiction
Changes (1)
- 2026-10-28 Added to the atlas Eatonton 379: Added to the atlas from a reviewed public project record.
Sources (4)
- DRI 4861: Eatonton 379 initial information form
- DRI 4861: Eatonton 379 information form part 2
- State of Georgia Counties - 2020 Census
- DCRA manual location approximation