Switch 300 Dell Way phase 2

Large colocation phase · Williamson County, TX

Switch, Ltd. · 300 Dell Way, Round Rock, TX

Status Phase 2 site-permit review remains open VERIFIED · HIGH Stage: Permitting / approvals
Last checked against its sources Oct 1, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

Switch's executed city agreement identifies 300 Dell Way as a separate 21.78-acre tract in its Round Rock campus. A May 2023 building application listed 183,605 square feet for Switch AUS NAP5. The city's current site-permit page still lists Switch RR Ph.2 in an applicant-action queue; this does not establish construction or operation. VERIFIED · HIGH

Key facts

Phase 2 site-permit tract
21.78 acres
VERIFIED · HIGH
2023 building application scope
183,605 ft²
VERIFIED · HIGH
Confirmed site electrical draw capacity (MW)
UNKNOWN
UNKNOWN · UNKNOWN
Confirmed serving electric utility
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (5)