Switch 300 Dell Way phase 2
Large colocation phase · Williamson County, TX
Status Phase 2 site-permit review remains open VERIFIED · HIGH Stage: Permitting / approvals
Last checked against its sources Oct 1, 2026
The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.
Profile
Switch's executed city agreement identifies 300 Dell Way as a separate 21.78-acre tract in its Round Rock campus. A May 2023 building application listed 183,605 square feet for Switch AUS NAP5. The city's current site-permit page still lists Switch RR Ph.2 in an applicant-action queue; this does not establish construction or operation. VERIFIED · HIGH
Key facts
- Phase 2 site-permit tract
- 21.78 acres
- VERIFIED · HIGH
- 2023 building application scope
- 183,605 ft²
- VERIFIED · HIGH
- Confirmed site electrical draw capacity (MW)
- UNKNOWN
- UNKNOWN · UNKNOWN
- Confirmed serving electric utility
- UNKNOWN
- UNKNOWN · UNKNOWN
VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.
Open questions
- UNKNOWN Final phase 2 site and building permit status, construction start, and service date
- UNKNOWN Site-specific power capacity, signed electric service, and serving utility
- UNKNOWN Generator authorization, cooling and water-use details, and response resources
Changes (1)
- 2026-10-01 Added to the atlas Switch 300 Dell Way phase 2: Added to the atlas.