PowerHouse Louisville

Hyperscale data center campus · Jefferson County, KY

PowerHouse Data Centers / Poe Companies

Status Construction activity reported VERIFIED · MODERATE Stage: Under construction
Last checked against its sources Sep 30, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

PowerHouse Data Centers and Poe Companies are developing a 154-acre Louisville campus. Two independent local reports describe construction activity. LG&E reported 335 MW of initially secured utility power in January 2025, while the developer targets power delivery in Q4 2026; operation and current draw remain unconfirmed. VERIFIED · MODERATE

Key facts

Initially secured utility power
335 MW secured (2025 announcement)
VERIFIED · MODERATE
Campus area
154 acres
VERIFIED · MODERATE
Power delivery target
Q4 2026
VERIFIED · MODERATE
Backup generation
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (2)

Sources (6)