Antelope Data Center

Proposed data center campus · Iron County, UT

Pronghorn Development, LLC

Status Conditional-use application in county review record VERIFIED · HIGH Stage: Permitting / approvals
Last checked against its sources Oct 4, 2026

Open in the interactive atlas →

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

Iron County listed Pronghorn Development's Antelope Data Center conditional-use application for a 640-acre site. The June 2026 agenda describes five proposed data-center buildings and an on-site natural-gas power plant scalable to 1,500 MW at full buildout. That generation figure is not confirmed facility draw, and the reviewed primary pages do not establish construction. VERIFIED · HIGH

Key facts

Proposed site area
640 acres
VERIFIED · HIGH
Proposed data-center buildings
5
VERIFIED · HIGH
Proposed on-site generation at full buildout
Up to 1,500 MW natural-gas generation
VERIFIED · HIGH
Facility electrical draw capacity (MW)
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (4)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.