TeraWulf Justified Data
- Under construction
- AI / HPC data center campus
- 8 sources
- Last checked Nov 14, 2026
Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Under construction; Fluor EPC agreement executed
- Sourced · fair
- Current phased delivery targets
- Late 2027 through Q2 2028
- Sourced · fair
- Approved electric service (issuer-reported)
- Up to 482 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). approved electric service (company filing)
- Sourced · fair
- Leased critical IT capacity
- ~401 MW leased to Anthropic
- Sourced · fair
- Buildable land
- More than 250 buildable acres
- Sourced · fair
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 3 terms used on this page
- IT lease
- A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- UPS (uninterruptible power supply)
- Batteries that keep computers running through the seconds between a power loss and backup generators starting.
Profile
TeraWulf announced acquisition of a former Hawesville industrial site with approximately 480 MW of existing power availability and more than 250 buildable acres. In July 2026, it announced an Anthropic lease for approximately 401 MW of critical IT lease: A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.. November filings report construction underway, 482 MW of approved electric service, Google credit support and a definitive Fluor EPC agreement; phased delivery is targeted for late 2027 through Q2 2028. Its August filing notes an on-site energized substation and transmission access; none of these figures is current consumption. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules · MISO
No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
- Not in the public record
- Backup generation
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Primary fire jurisdiction
- Not in the public record
Fire and rescue stations (215)
| Name | Straight-line distance | Role |
|---|---|---|
| Hawesville Fire Department | 4.7 mi NNE | Nearby origin |
| Dukes Fire Department | 5.3 mi ESE | Nearby origin |
| Cannelton Volunteer Fire Department | 5.5 mi NNE | Nearby origin |
| South Hancock Fire Department | 6.4 mi S | Nearby origin |
| Tell City Volunteer Fire Department | 7.6 mi NNE | Nearby origin |
| Knottsville Volunteer Fire Department | 7.9 mi SW | Nearby origin |
| Cloverport City Fire Department | 8.4 mi E | Nearby origin |
| Lewisport Fire Department | 8.6 mi NW | Nearby origin |
| Yelvington Volunteer Fire Department | 9.5 mi W | Nearby origin |
| Troy Volunteer Fire Department | 11 mi N | Nearby origin |
Hospitals (21)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Perry County Memorial Hospital | 9.2 mi NNE | Not in the public record |
| Owensboro Health Regional Hospital | 15 mi WSW | Not in the public record |
| Breckinridge Memorial Hospital | 20 mi ESE | Not in the public record |
| River Valley Behavioral Health Children's Hospital - Owensboro | 20 mi WSW | Not in the public record |
| Ohio County Hospital | 28 mi SSW | Not in the public record |
| Ascension Saint Vincent Warrick Hospital | 29 mi WNW | Not in the public record |
| Encompass Health Deaconess Rehabilitation Hospital | 35 mi WNW | Not in the public record |
| Deaconess Gateway Hospital | 37 mi WNW | Not in the public record |
| The Women's Hospital | 37 mi WNW | Not in the public record |
| Twin Lakes Regional Medical Center | 38 mi SE | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Exact campus point and independently verified construction progress
- Named serving utility and physical transmission route
- Backup generation, battery systems, and facility water use
- Local response resources not yet recorded
Changes (3)
- 2026-11-14 Permit / regulatory TeraWulf Justified Data: Added the PSC order on the service agreement: Kenergy retail service with Big Rivers buying through MISO, curtailment terms, and about 10 MW of emergency generation. Source: Kentucky Public Service Commission.
- 2026-11-14 Project status TeraWulf Justified Data: November issuer filing explicitly reports campus-wide construction underway; approved service is reported at 482 MW, with delivery targeted for late 2027 through Q2 2028. Google credit support and Fluor EPC agreements are recorded. Previously: Development; PROPOSED; 480 MW gross availability in the earlier company announcement. Source: TeraWulf Inc.; TeraWulf Inc. / U.S. Securities and Exchange Commission. Public submission.
- 2026-09-26 Added to the atlas TeraWulf Justified Data: Added to the atlas.
Related data centers
More from TeraWulf Inc.
Others in Kentucky
Cite this record
"TeraWulf Justified Data", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/terawulf-justified-hawesville, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.