TeraWulf Justified Data

TeraWulf Inc. · Hancock County, Kentucky

Open in the interactive atlas →

Key facts

Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.

What the labels mean
Sourced
A cited source states it. Open the source to see who said it.
Calculated
DCRA calculated it from sourced values. The math is shown.
Estimate
An approximation where no source states the value.
Modeled
Output of an illustrative planning scenario. Not a forecast.
Unknown
Not in the public record. Unknown, not absent.
Sourced · strong
Strong: read directly in a primary record, such as a filing or the company's own release.
Sourced · fair
Fair: a company statement of its own plans, an official's written reply, or a solid report.
Sourced · weak
Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.

The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.

Status
Under construction; Fluor EPC agreement executed
Sourced · fair
Current phased delivery targets
Late 2027 through Q2 2028
Sourced · fair
Approved electric service (issuer-reported)
Up to 482 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). approved electric service (company filing)
Sourced · fair
Leased critical IT capacity
~401 MW leased to Anthropic
Sourced · fair
Buildable land
More than 250 buildable acres
Sourced · fair

"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.

Plain-language glossary: 3 terms used on this page
IT lease
A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.
MW (megawatt)
A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
UPS (uninterruptible power supply)
Batteries that keep computers running through the seconds between a power loss and backup generators starting.

Profile

TeraWulf announced acquisition of a former Hawesville industrial site with approximately 480 MW of existing power availability and more than 250 buildable acres. In July 2026, it announced an Anthropic lease for approximately 401 MW of critical IT lease: A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.. November filings report construction underway, 482 MW of approved electric service, Google credit support and a definitive Fluor EPC agreement; phased delivery is targeted for late 2027 through Q2 2028. Its August filing notes an on-site energized substation and transmission access; none of these figures is current consumption. Sourced · fair

Power and the grid

What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.

Loading grid records…

Published grid documents and the capacity comparison are in the interactive atlas, under Energy.

Who pays for the grid equipment

Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.

Filed grid projects

No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.

Who pays for this facility's connection

Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.

The rules · MISO

No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.

Hazards

Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.

What this facility's record says

Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
Not in the public record
Backup generation
Not in the public record

Emergency response

The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.

Fire jurisdiction

Primary fire jurisdiction
Not in the public record

Fire and rescue stations (215)

NameStraight-line distanceRole
Hawesville Fire Department
Hawesville Volunteer Fire Department
4.7 mi NNENearby origin
Dukes Fire Department
Dukes Volunteer Fire Department
5.3 mi ESENearby origin
Cannelton Volunteer Fire Department5.5 mi NNENearby origin
South Hancock Fire Department
South Hancock Volunteer Fire Department
6.4 mi SNearby origin
Tell City Volunteer Fire Department7.6 mi NNENearby origin
Knottsville Volunteer Fire Department
Daviess County Fire Department
7.9 mi SWNearby origin
Cloverport City Fire Department
Cloverport Fire Department
8.4 mi ENearby origin
Lewisport Fire Department
Lewisport Volunteer Fire Department
8.6 mi NWNearby origin
Yelvington Volunteer Fire Department
Daviess County Fire Department
9.5 mi WNearby origin
Troy Volunteer Fire Department
Troy Fire Department
11 mi NNearby origin

The nearest 10 of 215. See all of them in the atlas →

Hospitals (21)

NameStraight-line distanceEmergency department
Perry County Memorial Hospital9.2 mi NNENot in the public record
Owensboro Health Regional Hospital15 mi WSWNot in the public record
Breckinridge Memorial Hospital20 mi ESENot in the public record
River Valley Behavioral Health Children's Hospital - Owensboro20 mi WSWNot in the public record
Ohio County Hospital28 mi SSWNot in the public record
Ascension Saint Vincent Warrick Hospital29 mi WNWNot in the public record
Encompass Health Deaconess Rehabilitation Hospital35 mi WNWNot in the public record
Deaconess Gateway Hospital37 mi WNWNot in the public record
The Women's Hospital37 mi WNWNot in the public record
Twin Lakes Regional Medical Center38 mi SENot in the public record

The nearest 10 of 21. See all of them in the atlas →

Distances: Calculated · weak

Sources for these stations and hospitals (2)

What this record is missing

No public source yet for:

  • Exact campus point and independently verified construction progress
  • Named serving utility and physical transmission route
  • Backup generation, battery systems, and facility water use
  • Local response resources not yet recorded

Changes (3)

Related data centers

More from TeraWulf Inc.

Others in Kentucky

Cite this record

"TeraWulf Justified Data", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/terawulf-justified-hawesville, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.