Vantage Frontier (Stargate Shackelford County)

AI campus · Shackelford County, TX

Vantage Data Centers; Oracle / OpenAI (Stargate)

Status Under construction · first building 2H 2026 target VERIFIED · MODERATE
Last checked against its sources Sep 24, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

Vantage announced Frontier, a 1,200-acre campus in Shackelford County planned for 1.4 GW of critical IT across ten single-story buildings (3.7 million ft²), with more than $25 billion of investment and liquid cooling. OpenAI named the site part of Stargate with Oracle. The first building was targeted for the second half of 2026. VERIFIED · MODERATE

Key facts

Planned critical IT
1,400 MW (IT load)
VERIFIED · HIGH
Campus footprint
1,200 acres announced
VERIFIED · HIGH
Announced investment
>$25 billion
VERIFIED · HIGH
Cooling approach
Liquid cooling (company)
VERIFIED · MODERATE

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (4)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.