Stargate Abilene (Crusoe)
- Partly in service
- AI campus
- 17 sources
- Last checked Nov 14, 2026
Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Partially operational
- Sourced · fair
- Campus power capacity
- 1,200 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). reported
- Sourced · fair
- Grid review status
- 1.2 GW interconnect fully approved (developer's statement)
- Sourced · fair
- Campus footprint
- ~800 acres reported
- Sourced · fair
- Operational IT (first buildings)
- >200 MW reported
- Sourced · fair
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 9 terms used on this page
- ERCOT (Electric Reliability Council of Texas)
- Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines.
- PUCT (Public Utility Commission of Texas)
- The state agency that regulates electric utilities, including the rules for who pays for grid equipment.
- TCRF (transmission cost recovery factor)
- A charge on Texas electric bills that passes changes in transmission costs on to customers, updated twice a year.
- SB 6 (Senate Bill 6)
- A state law setting rules for very large electricity users, including what they must pay toward their own grid connection.
- IT lease
- A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.
- Interconnection agreement
- The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for.
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- kV (kilovolt)
- A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances.
- UPS (uninterruptible power supply)
- Batteries that keep computers running through the seconds between a power loss and backup generators starting.
Profile
Crusoe-developed AI campus at the Lancium Clean Campus in Abilene serving Oracle Cloud Infrastructure for OpenAI. Reported at 1.2 GW across about 800 acres, with the first buildings online at more than 200 MW of IT lease: A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
4 name Stargate Abilene (Crusoe) or its developer; 6 are area projects that name no customer.
- Mulberry Creek: new 345 kV terminalNames the developer
- Size
- 345 kV · 2.25 new circuit miles
- Timing
- In service 2025-12
- Filed cost
- UNKNOWN · not published
Connects the Lancium load to AEP's Mulberry Creek 345 (kilovolt)kV (kilovolt): A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances. station.
The row names the Lancium load. Its December 2025 in-service date matches the contractor's account of the campus's 345 kV substation first energizing on December 19, 2025.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT)Mortenson - Mulberry Creek: expand 345 kV stationNames the developer
- Size
- 345 kV · 2.5 new circuit miles
- Timing
- Planned · projected 2028-12
- Filed cost
- UNKNOWN · not published
Expands the Mulberry Creek 345 kV station to connect the Lancium load.
The row names the Lancium load, not a campus. Lancium has other loads in the list, and no document read by DCRA says whether this project serves Stargate Abilene or another Lancium site in Taylor County.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Jacaranda: new 345 kV station with two transformersNames the developer
- Size
- 345 kV · 900 MVA · 3 new circuit miles
- Timing
- Planned · projected 2029-04
- Filed cost
- UNKNOWN · not published
Builds a new Jacaranda 345 kV station and installs two autotransformers to connect the Lancium load.
The row names the Lancium load, not a campus. Lancium has other loads in the list, and no document read by DCRA says whether this project serves Stargate Abilene or another Lancium site in Taylor County.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Vitex: new 345 kV stationNames the developer
- Size
- 345 kV · 15 new circuit miles
- Timing
- Planned · projected 2029-10
- Filed cost
- UNKNOWN · not published
Builds a new Vitex 345 kV station on the Bluff Creek to Mulberry Creek 345 kV line to connect the Lancium load.
The row names the Lancium load, not a campus. Lancium has other loads in the list, and no document read by DCRA says whether this project serves Stargate Abilene or another Lancium site in Taylor County.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Abilene Northwest to Mulberry Creek: rebuild 138 kV lineArea project
- Size
- 138 kV
- Timing
- Planned · projected 2027-01
- Filed cost
- UNKNOWN · not published
Rebuilds 2.58 circuit miles of the Abilene Northwest to Mulberry Creek 138 kV line.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Elm Creek to Mulberry Creek: rebuild 138 kV lineArea project
- Size
- 138 kV
- Timing
- Planned · projected 2027-05
- Filed cost
- UNKNOWN · not published
Rebuilds 5.7 circuit miles of the Elm Creek to Mulberry Creek 138 kV line.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Mulberry Creek: rebuild 138 kV stationArea project
- Size
- 138 kV
- Timing
- Planned · projected 2027-11
- Filed cost
- UNKNOWN · not published
Rebuilds the Mulberry Creek 138 kV station. (Electric Reliability Council of Texas)ERCOT (Electric Reliability Council of Texas): Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines.'s regional planning review 25RPG034 was completed in October 2025.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Jacaranda to Mulberry Creek: two new 345 kV linesArea project
- Size
- 345 kV · 6 new circuit miles
- Timing
- Planned · projected 2029-04
- Filed cost
- UNKNOWN · not published
Builds two new 345 kV lines between the Jacaranda and Mulberry Creek stations.
The row names no customer. It shares the utility's project number (TP2026088) with the Jacaranda station, which is for the Lancium load.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Jacaranda to Paulownia (Oncor): two new 345 kV linesArea project
- Size
- 345 kV · 0.2 new circuit miles
- Timing
- Planned · projected 2029-04
- Filed cost
- UNKNOWN · not published
Builds two new 345 kV lines between the Jacaranda station and Oncor's Paulownia station.
The row names no customer. It shares the utility's project number (TP2026088) with the Jacaranda station, which is for the Lancium load.
ERCOT's public project list is the "No Cost" version; no filed document read by DCRA states this project's cost.
Sourced · strongElectric Reliability Council of Texas (ERCOT) - Panhandle 765 kV loop through Mulberry Creek (utility's preferred option)Area project
- Size
- 765 kV · 632 new circuit miles
- Timing
- Proposed, not approved
- Filed cost
- $11.485 billion (2026 dollars)
AEP's proposal for a new 765 kV loop of about 632 miles linking Mulberry Creek with stations to the north and east, to serve over 25 GW of large loads it has agreed to connect in the Panhandle region. It needs new right of way and a state route approval.
A regional proposal that names no customer. The utility's table splits the cost as ETT $5.160 billion, AEP Texas $3.146 billion, and Oncor $3.178 billion. It is not approved, and none of it is assigned to any one facility.
Sourced · strongAEP Service Corporation, posted by ERCOT
An area project serves many customers. Its cost is not this facility's cost, and DCRA does not divide it.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules · ERCOT, TX
- New lines and transmission substations In force
- Pays: Electricity users across the grid region. Equipment at 60 kV and above is paid for by electricity users across all of ERCOT, not only nearby. Each transmission utility's approved cost is shared among every distribution utility in ERCOT by its share of the summer peak. Sourced · strongPublic Utility Commission of Texas
- On household bills In force
- Pays: The utility's customers. Distribution utilities pass changes in those transmission charges on to their customers twice a year. Sourced · strongPublic Utility Commission of Texas
- What a large data center pays itself In force
- Pays: The data center or its developer. Texas (Senate Bill 6)SB 6 (Senate Bill 6): A state law setting rules for very large electricity users, including what they must pay toward their own grid connection. (2025) requires loads of 75 MW and up (the default threshold) to contribute to the utility's cost of connecting them, pay a screening study fee of at least $100,000, and post financial security for transmission built to serve them. Sourced · strongTexas Legislature
- Proposed change Proposed
- Pays: Electricity users across the grid region. In July 2026 the (Public Utility Commission of Texas)PUCT (Public Utility Commission of Texas): The state agency that regulates electric utilities, including the rules for who pays for grid equipment. proposed sharing transmission cost by 12 monthly peaks instead of 4 summer ones, with a minimum bill for large loads. Adoption is not confirmed. Sourced · strongPublic Utility Commission of Texas (Texas Register, July 24, 2026)
- This facility's share
- Unknown How much of any planned line or upgrade a single facility pays is not published; the rules above name no customer.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
- Not in the public record
- Backup generation
- Natural gas turbines (company) · see on-site generation permit
- Sourced · fair
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Primary fire jurisdiction
- Not in the public record
Fire and rescue stations (47)
| Name | Straight-line distance | Role |
|---|---|---|
| Abilene Fire Department Station 4 | 2.5 mi ESE | Nearby origin |
| Abilene Fire Department Station 7 | 3.7 mi S | Nearby origin |
| Abilene Fire Department Station 1 | 4.6 mi SSE | Nearby origin |
| Abilene Fire Department Station 5 | 5.4 mi SE | Nearby origin |
| Abilene Fire Department Station 6 | 5.8 mi S | Nearby origin |
| Abilene Fire Department Station 3 | 5.9 mi SSE | Nearby origin |
| Tye Volunteer Fire Department Station 1 | 6.3 mi SW | Nearby origin |
| Tye Volunteer Fire Department Station 2 | 6.7 mi SW | Nearby origin |
| Hawley Volunteer Fire Department | 7.4 mi NNW | Nearby origin |
| Abilene Fire Department Station 2 | 7.7 mi SSE | Nearby origin |
Hospitals (6)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Hendrick Medical Center | 3.8 mi SE | Not in the public record |
| Hendrick Medical Center South | 9.6 mi SSE | Not in the public record |
| Rolling Plains Memorial Hospital | 36 mi W | Not in the public record |
| North Runnels Hospital | 40 mi SSW | Not in the public record |
| Fisher County Hospital | 44 mi WNW | Not in the public record |
| Haskell Memorial Hospital | 45 mi N | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Local response resources not yet recorded
- Battery and solar size undisclosed; installed (as opposed to permitted) generation not confirmed
- Cost of each grid project and this facility's share
- Water supplier
Changes (3)
- 2026-11-14 New information Stargate Abilene (Crusoe): Added the grid connection (AEP Texas, Mulberry Creek 345 kV station, 1.2 GW grid interconnection), 360.5 MW of permitted on-site gas turbines, the city's tax abatement terms, and ten filed grid projects with who pays for them. No project's cost is published except a proposed $11.485 billion regional 765 kV loop, which is not assigned to any facility. Source: Electric Reliability Council of Texas (ERCOT); AEP Service Corporation, posted by ERCOT; Texas Commission on Environmental Quality (TCEQ); Crusoe; City of Abilene.
- 2026-11-02 New information Stargate Abilene (Crusoe): Added grid documents: the developer's statements that the campus has a 1.2 GW interconnect fully approved by ERCOT (not confirmed by an ERCOT or AEP Texas record), draft air permits for a Crusoe power plant in Abilene, and a contractor's account of substation work. Source: Lancium, filed at the PUCT; Texas Commission on Environmental Quality (TCEQ); Mortenson.
- 2026-09-23 Added to the atlas Stargate Abilene (Crusoe): Added to the atlas.
Related data centers
Others in Texas
Cite this record
"Stargate Abilene (Crusoe)", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/crusoe-stargate-abilene, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.