Galaxy Helios

Galaxy Digital Inc.; CoreWeave (tenant) · Dickens County, Texas

Open in the interactive atlas →

Key facts

Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.

What the labels mean
Sourced
A cited source states it. Open the source to see who said it.
Calculated
DCRA calculated it from sourced values. The math is shown.
Estimate
An approximation where no source states the value.
Modeled
Output of an illustrative planning scenario. Not a forecast.
Unknown
Not in the public record. Unknown, not absent.
Sourced · strong
Strong: read directly in a primary record, such as a filing or the company's own release.
Sourced · fair
Fair: a company statement of its own plans, an official's written reply, or a solid report.
Sourced · weak
Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.

The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.

Status
Phase I delivered · expanding
Sourced · fair
(Electric Reliability Council of Texas)ERCOT (Electric Reliability Council of Texas): Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines.-approved capacity
1,630 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). approved
Sourced · strong
Delivered critical IT (Phase I)
133 MW IT (200 MW gross)
Sourced · fair
Campus footprint
1,500+ acres
Sourced · fair
Tenant
CoreWeave (15-year leases)
Sourced · strong

"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.

Plain-language glossary: 8 terms used on this page
ERCOT (Electric Reliability Council of Texas)
Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines.
PUCT (Public Utility Commission of Texas)
The state agency that regulates electric utilities, including the rules for who pays for grid equipment.
TCRF (transmission cost recovery factor)
A charge on Texas electric bills that passes changes in transmission costs on to customers, updated twice a year.
SB 6 (Senate Bill 6)
A state law setting rules for very large electricity users, including what they must pay toward their own grid connection.
Interconnection agreement
The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for.
MW (megawatt)
A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
kV (kilovolt)
A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances.
UPS (uninterruptible power supply)
Batteries that keep computers running through the seconds between a power loss and backup generators starting.

Profile

Galaxy's Helios campus in Dickens County, about 60 miles from Lubbock, has 1,630 MW of ERCOT-approved capacity. Phase I (133 MW of critical IT, 200 MW gross) was delivered to CoreWeave in 2026 under 15-year leases. Sourced · fair

Power and the grid

What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.

Loading grid records…

Published grid documents and the capacity comparison are in the interactive atlas, under Energy.

Who pays for the grid equipment

Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.

Filed grid projects

No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.

Who pays for this facility's connection

Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.

The rules · ERCOT, TX

New lines and transmission substations In force
Pays: Electricity users across the grid region. Equipment at 60 (kilovolt)kV (kilovolt): A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances. and above is paid for by electricity users across all of ERCOT, not only nearby. Each transmission utility's approved cost is shared among every distribution utility in ERCOT by its share of the summer peak. Sourced · strongPublic Utility Commission of Texas
On household bills In force
Pays: The utility's customers. Distribution utilities pass changes in those transmission charges on to their customers twice a year. Sourced · strongPublic Utility Commission of Texas
What a large data center pays itself In force
Pays: The data center or its developer. Texas (Senate Bill 6)SB 6 (Senate Bill 6): A state law setting rules for very large electricity users, including what they must pay toward their own grid connection. (2025) requires loads of 75 MW and up (the default threshold) to contribute to the utility's cost of connecting them, pay a screening study fee of at least $100,000, and post financial security for transmission built to serve them. Sourced · strongTexas Legislature
Proposed change Proposed
Pays: Electricity users across the grid region. In July 2026 the (Public Utility Commission of Texas)PUCT (Public Utility Commission of Texas): The state agency that regulates electric utilities, including the rules for who pays for grid equipment. proposed sharing transmission cost by 12 monthly peaks instead of 4 summer ones, with a minimum bill for large loads. Adoption is not confirmed. Sourced · strongPublic Utility Commission of Texas (Texas Register, July 24, 2026)
This facility's share
Unknown How much of any planned line or upgrade a single facility pays is not published; the rules above name no customer.

Hazards

Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.

What this facility's record says

Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
Not in the public record
Backup generation
Not in the public record

Emergency response

The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.

Fire jurisdiction

Primary fire jurisdiction
Not in the public record

Fire and rescue stations (14)

NameStraight-line distanceRole
Dickens Volunteer Fire Department0.5 mi ENENearby origin
Spur Volunteer Fire Department10 mi SNearby origin
Matador Volunteer Fire Department
Matador/Motley County Volunteer Fire Department
27 mi NPotential mutual-aid origin
Ralls Volunteer Fire Department31 mi WPotential mutual-aid origin
Floydada Volunteer Fire Department38 mi NWPotential mutual-aid origin
Lorenzo Volunteer Fire Department and Emergency Medical Services
Lorenzo Volunteer Fire Department
40 mi WPotential mutual-aid origin
Paducah Volunteer Fire Department41 mi NEPotential mutual-aid origin
Post Volunteer Fire Department43 mi SWPotential mutual-aid origin
Petersburg Volunteer Emergency Medical Services47 mi WNWPotential mutual-aid origin
Slaton Fire Department48 mi WSWPotential mutual-aid origin

The nearest 10 of 14. See all of them in the atlas →

Hospitals (2)

NameStraight-line distanceEmergency department
Stonewall Memorial Hospital48 mi SENot in the public record
W J Mangold Memorial Hospital49 mi NWNot in the public record

Distances: Calculated · weak

Sources for these stations and hospitals (2)

What this record is missing

No public source yet for:

  • Site location (only a county-level point is shown)
  • Cooling method and water source
  • Local response resources not yet recorded

Changes (1)

Related data centers

Others in Texas

Cite this record

"Galaxy Helios", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/galaxy-helios, last checked Sep 24, 2026. Licensed under CC BY-NC 4.0.

Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.