IREN Sweetwater 1

AI data center site · Nolan County, TX

IREN Ltd

Status Substation energized · halls under construction VERIFIED · HIGH
Last checked against its sources Sep 24, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

IREN's Sweetwater 1 is a 1.4 GW site whose high-voltage substation was connected to the ERCOT grid in May 2026. Construction of 300 MW (gross) of data center capacity is targeted for Q4 2027. With Sweetwater 2 (600 MW, about 28 miles away) it forms IREN's 2 GW Sweetwater hub, which the company says was conditionally included in ERCOT's Batch Zero process. VERIFIED · MODERATE

Key facts

Grid connection capacity
1,400 MW
VERIFIED · HIGH
Substation energized
May 2026
VERIFIED · HIGH
First data center phase (target)
300 MW gross · Q4 2027 target
VERIFIED · MODERATE
ERCOT large-load process
Batch Zero · conditional, as base load
VERIFIED · MODERATE

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (6)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.