Cipher Barber Lake
- Under construction
- AI hosting campus
- 13 sources
- Last checked Nov 14, 2026
Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Under construction; phased delivery targeted Q4 2026–Q1 2027
- Sourced · fair
- Contracted lease duration
- 20 years
- Sourced · fair
- (Electric Reliability Council of Texas)ERCOT (Electric Reliability Council of Texas): Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines. Interconnection agreement: The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for. approval
- Up to 300 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- Sourced · strong
- Initial IT lease: A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.
- 168 MW IT (244 MW gross)
- Sourced · strong
- Site area
- 587 acres
- Sourced · strong
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 11 terms used on this page
- ERCOT (Electric Reliability Council of Texas)
- Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines.
- PUCT (Public Utility Commission of Texas)
- The state agency that regulates electric utilities, including the rules for who pays for grid equipment.
- TCRF (transmission cost recovery factor)
- A charge on Texas electric bills that passes changes in transmission costs on to customers, updated twice a year.
- SB 6 (Senate Bill 6)
- A state law setting rules for very large electricity users, including what they must pay toward their own grid connection.
- IT lease
- A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.
- Interconnection agreement
- The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for.
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- kV (kilovolt)
- A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances.
- UPS (uninterruptible power supply)
- Batteries that keep computers running through the seconds between a power loss and backup generators starting.
- Data hall delivery
- When finished computer rooms are handed over to the tenant.
- Fire flow
- How much water the local water system can deliver to fight a fire at a site, and for how long.
Profile
Cipher's Barber Lake site near Colorado City covers 587 acres with ERCOT interconnection approval up to 300 MW and an energized substation. The September 25 amendment extends contracted duration to 20 years through the Fluidstack lease and a subsequent AI-lab commitment, with phased delivery targeted for Q4 2026–Q1 2027. The original agreement starts with 168 MW of critical IT, and Google backstops $1.4 billion of the lease obligations. The company states the site uses its own water supply and draws nothing from the city system. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules · ERCOT, TX
- New lines and transmission substations In force
- Pays: Electricity users across the grid region. Equipment at 60 (kilovolt)kV (kilovolt): A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances. and above is paid for by electricity users across all of ERCOT, not only nearby. Each transmission utility's approved cost is shared among every distribution utility in ERCOT by its share of the summer peak. Sourced · strongPublic Utility Commission of Texas
- On household bills In force
- Pays: The utility's customers. Distribution utilities pass changes in those transmission charges on to their customers twice a year. Sourced · strongPublic Utility Commission of Texas
- What a large data center pays itself In force
- Pays: The data center or its developer. Texas (Senate Bill 6)SB 6 (Senate Bill 6): A state law setting rules for very large electricity users, including what they must pay toward their own grid connection. (2025) requires loads of 75 MW and up (the default threshold) to contribute to the utility's cost of connecting them, pay a screening study fee of at least $100,000, and post financial security for transmission built to serve them. Sourced · strongTexas Legislature
- Proposed change Proposed
- Pays: Electricity users across the grid region. In July 2026 the (Public Utility Commission of Texas)PUCT (Public Utility Commission of Texas): The state agency that regulates electric utilities, including the rules for who pays for grid equipment. proposed sharing transmission cost by 12 monthly peaks instead of 4 summer ones, with a minimum bill for large loads. Adoption is not confirmed. Sourced · strongPublic Utility Commission of Texas (Texas Register, July 24, 2026)
- This facility's share
- Unknown How much of any planned line or upgrade a single facility pays is not published; the rules above name no customer.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
- Not in the public record
- Backup generation
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Fire jurisdiction
- Colorado City Fire Department (NERIS boundary)
- Calculated · weak
- Jurisdiction department type
- Combination
- Sourced · fair
- Department staffing
- 5 career full-time · 28 volunteer firefighters
- Sourced · fair
- Department stations
- 1 station
- Sourced · fair
- Services the department lists
- Not in the public record
Fire and rescue stations (30)
| Name | Straight-line distance | Role |
|---|---|---|
| Colorado City Fire Department | 1.2 mi E | Nearby origin |
| Westbrook Volunteer Fire Department | 8.3 mi WSW | Nearby origin |
| Roscoe Volunteer Fire Department | 20 mi E | Potential mutual-aid origin |
| Snyder Fire Department | 22 mi N | Potential mutual-aid origin |
| Howard County Volunteer Fire Department Coahoma | 26 mi WSW | Potential mutual-aid origin |
| Maryneal Volunteer Fire Department | 28 mi ESE | Potential mutual-aid origin |
| Sweetwater Fire Department | 28 mi E | Potential mutual-aid origin |
| Howard County Volunteer Fire Department Sand Springs | 29 mi WSW | Potential mutual-aid origin |
| Lake Sweetwater Volunteer Fire Department | 34 mi E | Potential mutual-aid origin |
| Howard County Volunteer Fire Department Forsan | 35 mi SW | Potential mutual-aid origin |
Hospitals (6)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Mitchell County Hospital | 0.5 mi NNE | Not in the public record |
| Cogdell Memorial Hospital | 20 mi N | Not in the public record |
| Rolling Plains Memorial Hospital | 28 mi E | Not in the public record |
| Big Spring State Hospital | 37 mi WSW | Not in the public record |
| Shannon Medical Center BIg Spring | 37 mi WSW | Not in the public record |
| Fisher County Hospital | 40 mi NE | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- On-site water source type, capacity, and Fire flow: How much water the local water system can deliver to fight a fire at a site, and for how long. availability
- Cooling method
- Local response resources not yet recorded
Changes (3)
- 2026-11-14 New information Cipher Barber Lake: Added Cipher's risk statement about batching of large load interconnection requests. Source: Cipher Digital (filed with the U.S. Securities and Exchange Commission).
- 2026-10-15 New information Cipher Barber Lake: September 25 amendment extends contracted duration to 20 years and shifts data-hall delivery targets to Q4 2026–Q1 2027; no completed delivery established. Source: Cipher Digital Inc. via GlobeNewswire. Public submission.
- 2026-09-24 Added to the atlas Cipher Barber Lake: Added to the atlas.
Related data centers
Others in Texas
Cite this record
"Cipher Barber Lake", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/cipher-barber-lake, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.