Atmosphere Dickerson Campus

Proposed hyperscale campus · Montgomery County, MD

Atmosphere Data Centers

Status Proposed / paused VERIFIED · MODERATE
Last checked against its sources Sep 26, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

The Atmosphere Dickerson Campus is a proposed 360 MW hyperscale data center development at the decommissioned Dickerson coal-fired power station in Montgomery County, Maryland. The proposal includes five buildings on approximately 110 to 170 acres, utilizing legacy power plant grid interconnections and proximity to Potomac fiber routes. Development is currently paused under Montgomery County's 18-month data center moratorium passed in July 2026. VERIFIED · MODERATE

Key facts

Planned campus capacity
360 MW planned capacity across 5 buildings
VERIFIED · MODERATE
Campus area
110–170 acre brownfield site
VERIFIED · MODERATE
Backup generation
UNKNOWN
UNKNOWN · UNKNOWN
Battery / UPS system
UNKNOWN
UNKNOWN · UNKNOWN

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (4)