PORTS-Pike Technology Campus

AI data center campus · Pike County, OH

SB Energy / SoftBank Group

Status Early civil works underway VERIFIED · MODERATE Stage: Under construction
Last checked against its sources Sep 30, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

DOE announced an SB Energy data-center development on the Portsmouth Site near Piketon in March 2026, with an initial phase on 189 acres. The developer says early civil works have begun and describes an approximately 800 MW first phase, with capacity expected online in phases beginning in 2028. These are plans, not current load or operating capacity; the separate generation program is not recorded as facility load. VERIFIED · MODERATE

Key facts

Announced first-phase scale
Approximately 800 MW planned
VERIFIED · MODERATE
Initial DOE site area
189 acres
VERIFIED · HIGH
First capacity target
2028
VERIFIED · MODERATE
Planned cooling
Closed-loop cooling
VERIFIED · MODERATE

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (5)