Microsoft ATL80

Proposed hyperscale campus · Floyd County, GA

Microsoft Corporation

Status DRI review filing; local approvals unresolved VERIFIED · MODERATE Stage: Permitting / approvals
Last checked against its sources Oct 28, 2026

Open in the interactive atlas →

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

Floyd County's DRI 4860 identifies Microsoft as developer of ATL80, a proposed three-building campus on 349.03 acres north of Huffaker Road. The energy form estimates 422 MW of peak connected load and names Georgia Power as the proposed supplier. These filing statements establish neither secured service nor completed construction. VERIFIED · MODERATE

Key facts

Filed site area
349.03 acres
VERIFIED · HIGH
Proposed data-center buildings
3
VERIFIED · HIGH
Filing estimate of peak connected electrical load
422 MW
ESTIMATED · MODERATE
Proposed backup generation
Backup diesel generators
VERIFIED · MODERATE

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (1)

Sources (4)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.