Switch Round Rock East Campus
- Proposed
- Proposed large colocation campus
- 7 sources
- Last checked Nov 14, 2026
Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- PUD 152 rezoning approved; construction unconfirmed
- Sourced · strong
- PUD 152 rezoning area
- 32.48 acres
- Sourced · strong
- Confirmed East Campus electrical draw capacity ( (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).)
- Not in the public record
- Confirmed serving electric utility
- Not in the public record
- East Campus site-permit status
- Not in the public record
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 1 terms used on this page
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
Profile
Round Rock approved a separate 32.48-acre Switch PUD north of Louis Henna Boulevard and east of Greenlawn Boulevard in October 2023. The city's project page identifies this as an expansion of Switch's Round Rock presence. The public records reviewed here do not establish a site permit, construction, contracted load, or service date for this tract. Sourced · strong
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules
No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Backup-generator type, count, and air permit
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Primary fire-response jurisdiction
- Not in the public record
Fire and rescue stations (231)
| Name | Straight-line distance | Role |
|---|---|---|
| Round Rock Fire Department Station 4 | 1.4 mi NE | Nearby origin |
| Round Rock Fire Department Station 3 | 1.5 mi WNW | Nearby origin |
| Travis County Emergency Services District Number 2 / Pflugerville Fire Department Station 4 | 1.7 mi SE | Nearby origin |
| Travis County ESD Number 2 / Pflugerville Fire Department Station 5 | 2.1 mi S | Nearby origin |
| Round Rock Fire Department Station 2 | 2.1 mi NW | Nearby origin |
| Travis County Emergency Services District Number 2 Pflugerville Fire Department Station 2 | 2.4 mi SW | Nearby origin |
| Round Rock Fire Department Station 5 | 2.9 mi WNW | Nearby origin |
| Round Rock Fire Station 8 | 3.0 mi ENE | Nearby origin |
| Round Rock Fire Department Station 6 | 3.0 mi NNE | Nearby origin |
| Round Rock Fire Department Central Station | 3.8 mi NNW | Nearby origin |
Hospitals (40)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Saint David's Round Rock Medical Center | 3.8 mi WNW | Not in the public record |
| Baylor Scott and White Medical Center - Pflugerville | 4.5 mi ESE | Not in the public record |
| Saint David's North Austin Medical Center | 5.7 mi SSW | Not in the public record |
| Baylor Scott and White Medical Center Round Rock | 5.8 mi NNW | Not in the public record |
| Ascension Seton Williamson Hospital | 5.8 mi N | Not in the public record |
| Ascension Seton Northwest Hospital | 7.4 mi SW | Not in the public record |
| Georgetown Behavioral Health Institute | 9.2 mi N | Not in the public record |
| Ascension Seton Cedar Park Hospital | 9.8 mi WNW | Not in the public record |
| Saint David's Georgetown Hospital | 10 mi N | Not in the public record |
| Northwest Hills Surgical Hospital | 11 mi SSW | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Current site and building permits, construction start, and service schedule
- East Campus capacity, utility service, and any substation commitment
- Backup generation, actual cooling and water use, and response resources
Changes (1)
- 2026-10-01 Added to the atlas Switch Round Rock East Campus: Added to the atlas.
Related data centers
More from Switch, Ltd.
Others in Texas
Cite this record
"Switch Round Rock East Campus", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/switch-round-rock-east-campus, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.