Google Haskell County (with Intersect Quantum)
Data center + co-located solar/storage · Haskell County, TX
Status Under construction · solar/storage operating VERIFIED · MODERATE
Last checked against its sources Sep 24, 2026
The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.
Profile
Google announced two data center campuses in Haskell County in November 2025 as part of a $40 billion Texas investment through 2027. One is co-located with Intersect's Quantum I and II solar and storage project (640 MW solar, 1.3 GWh battery storage), which began operating in June 2026 while the data center was under construction. VERIFIED · MODERATE
Key facts
- Co-located solar
- 640 MW (Quantum I & II)
- VERIFIED · MODERATE
- Co-located battery storage
- 1.3 GWh
- VERIFIED · MODERATE
- Solar/storage operations began
- June 2026
- VERIFIED · MODERATE
- Announced program
- Two Haskell County campuses; part of $40B Texas investment through 2027
- VERIFIED · HIGH
VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.
Open questions
- UNKNOWN Site locations (only a county-level point is shown)
- UNKNOWN Data center power capacity (MW)
- UNKNOWN Battery chemistry and layout at the co-located storage site
- UNKNOWN Local response resources not yet recorded
Changes (1)
- 2026-09-24 Added to the atlas Google Haskell County (with Intersect Quantum): Added to the atlas.
Sources (3)
- Google announces new $40 billion investment in Texas
- Intersect | Quantum
- DCRA manual location approximation