Hut 8 Beacon Point

Hut 8 Corp. · Nueces County, Texas

Open in the interactive atlas →Company project page ↗

The bottom line

Hut 8 is building an AI data center campus on 525 announced acres in unincorporated Nueces County, near Robstown and Calallen, with an AEP Texas Interconnection agreement: The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for. for 1,000 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh). of Utility capacity: The most power the grid connection is sized to deliver: the size of the pipe. Draw is how much is flowing at a given moment, and is usually lower. and both of its 352 MW IT lease: A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load. signed.10,16,24,28

The company says Phase 1 foundations and underground utilities were under way on November 4, 2026, and it targets first power from the grid (initial Energization: The first time power flows to a new site from the grid. It comes before full operation.) in Q1 2027 and finished Data hall delivery: When finished computer rooms are handed over to the tenant. in Q3 2027 and Q2 2028; DCRA has not independently confirmed that progress.1,8,16

Where the campus ties into the grid is not public: Hut 8's filings say an on-site substation is under construction, but no AEP Texas or (Electric Reliability Council of Texas)ERCOT (Electric Reliability Council of Texas): Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines. record DCRA found names its owner, its voltage, or the lines that will serve it.8,11,14

Hut 8 says it pre-funded the grid equipment that serves the campus and does not expect the project to raise household bills, but DCRA found no utility or regulator record of the payment, and this facility's share of shared grid costs is unknown.20,24

In October 2026 the local fire chief (Nueces County (Emergency Services District)ESD (Emergency Services District): A Texas local taxing district that funds fire and emergency service, often outside city limits. Nueces County ESD #1 runs the Annaville Fire Department.) wrote that containment of firefighting runoff had not been addressed yet and that the City of Corpus Christi's fire-code review, including Fire flow: How much water the local water system can deliver to fight a fire at a site, and for how long., was still under way.3

Where to look next: How these numbers fit · Timeline · Who pays · Hazards · Emergency response · Public bodies · What this record is missing · Changes · Sources

A summary of the sourced record below as of Nov 16, 2026. It adds no findings; each sentence links its sources.

Key facts

Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.

What the labels mean
Sourced
A cited source states it. Open the source to see who said it.
Calculated
DCRA calculated it from sourced values. The math is shown.
Estimate
An approximation where no source states the value.
Modeled
Output of an illustrative planning scenario. Not a forecast.
Unknown
Not in the public record. Unknown, not absent.
Sourced · strong
Strong: read directly in a primary record, such as a filing or the company's own release.
Sourced · fair
Fair: a company statement of its own plans, an official's written reply, or a solid report.
Sourced · weak
Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.

The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.

Status
Under construction · fully leased
Sourced · fair
Utility capacity
1,000 MW announced
Sourced · strong
Campus footprint
525 acres announced
Sourced · strong
Phase 1 IT lease
352 MW
Sourced · strong
Filed building scope
657,130 ft²
Sourced · fair
Registered building: filed end
November 2027
Sourced · fair
Battery / UPS system
Batteries in design · type UNKNOWN
Sourced · fair

"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.

Plain-language glossary: 22 terms used on this page
ERCOT (Electric Reliability Council of Texas)
Runs the power grid that serves most of Texas and reviews requests to connect very large new users. It does not own power lines.
PUCT (Public Utility Commission of Texas)
The state agency that regulates electric utilities, including the rules for who pays for grid equipment.
TDLR (Texas Department of Licensing and Regulation)
The state agency where building projects register for accessibility review. A registration lists a building's size, estimated cost, and planned dates; it does not show that permits were issued or work was done.
ESD (Emergency Services District)
A Texas local taxing district that funds fire and emergency service, often outside city limits. Nueces County ESD #1 runs the Annaville Fire Department.
RTFC (Refinery Terminal Fire Company)
A private industrial fire-protection company based in Corpus Christi.
Mutual aid
An arrangement for neighboring fire departments to send help to each other when asked.
TCRF (transmission cost recovery factor)
A charge on Texas electric bills that passes changes in transmission costs on to customers, updated twice a year.
SB 6 (Senate Bill 6)
A state law setting rules for very large electricity users, including what they must pay toward their own grid connection.
IT lease
A lease measured by the power the tenant's computers use (the IT load). The campus also needs power for cooling and other equipment, so its grid connection is larger than its IT load.
Utility capacity
The most power the grid connection is sized to deliver: the size of the pipe. Draw is how much is flowing at a given moment, and is usually lower.
Interconnection agreement
The contract with the utility to connect a large user to the grid, setting how much power the connection is sized for.
MW (megawatt)
A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
kV (kilovolt)
A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances.
UPS (uninterruptible power supply)
Batteries that keep computers running through the seconds between a power loss and backup generators starting.
Energization
The first time power flows to a new site from the grid. It comes before full operation.
Data hall delivery
When finished computer rooms are handed over to the tenant.
Fire flow
How much water the local water system can deliver to fight a fire at a site, and for how long.
Closed-loop cooling
A cooling system that recirculates the same water instead of drawing new water continuously.
Contribution in aid of construction
A payment a customer makes to a utility to cover the cost of building the equipment that serves it.
Reinvestment zone
An area a Texas county or city must designate before it can offer a property-tax abatement there.
High-investment-grade tenant
A company's way of saying its tenant has a strong credit rating. It does not name the tenant.
Base-term contract value
The total a tenant is committed to pay over the lease's initial term. It is revenue to the owner, not the cost to build.

How these numbers fit

Power

  • 1,000 MW is the utility capacity in Hut 8's interconnection agreement with AEP Texas: the size of the pipe, the most power the grid connection is sized to deliver. It is not how much the campus draws today.16,24 Sourced · strong
  • 352 MW is the computer load (IT load) in each of the two leases. Together they make 704 MW.10,16 Sourced · strong
  • Hut 8 says the first 352 MW lease needs about 500 MW of utility capacity. It has not stated the figure for the second lease.16 Sourced · strong
  • If the second lease needs the same as the first, the two leases need about 1,000 MW, which matches the agreement and the company's description of the campus as fully leased.10,16 Calculated · fairMath: 2 leases × about 500 MW each = about 1,000 MW. Assumes the second lease needs the same utility capacity as the first, which Hut 8 has not stated.

Money: three figures that measure different things

  • $19.6 billion is the Base-term contract value: The total a tenant is committed to pay over the lease's initial term. It is revenue to the owner, not the cost to build. of the two 15-year leases ($9.8 billion for the first): what the tenant is committed to pay Hut 8 over those terms. It is revenue to Hut 8, not the cost to build.10,16 Sourced · strong
  • $399 million is the estimated cost on the state TDLR registration for one registered scope of 657,130 ft². It is not the cost of the whole campus.31 Sourced · fair
  • $4.25 billion is borrowed money: Hut 8's June 2026 SEC filing announced pricing of that amount in senior secured notes for the project. Borrowing is not the same as the cost to build.14 Sourced · fair

Timeline

Company targets and public filings are marked separately. A target is the company's plan, not a commitment.

  1. Sep 2026Filed building work beginsPublic filing Sourced · fair29,31One registered building scope, not the whole campus.
  2. Q1 2027First power from the grid (initial energization)Company says Sourced · strong8,16Company target, not a commitment.
  3. Q3 2027Phase 1 data halls deliveredCompany says Sourced · fair1Company target, not a commitment.
  4. Nov 2027Filed building work endsPublic filing Sourced · fair29,31One registered building scope. A filing does not guarantee completion.
  5. Q2 2028Phase 2 data halls deliveredCompany says Sourced · fair1Company target, not a commitment.

Profile

Hut 8 is developing Beacon Point, an announced 525-acre AI data center campus near Robstown and Calallen in unincorporated Nueces County. The company reports an executed interconnection agreement for 1 GW of utility capacity, initial energization targeted for Q1 2027, and preliminary data hall delivery targeted for Q3 2027. Sourced · strong

Two 15-year, 352 MW IT leases with one undisclosed High-investment-grade tenant: A company's way of saying its tenant has a strong credit rating. It does not name the tenant. tenant bring contracted IT capacity to 704 MW and campus base-term contract value to $19.6 billion (company disclosures, May and July 2026). Sourced · strong

A (Texas Department of Licensing and Regulation)TDLR (Texas Department of Licensing and Regulation): The state agency where building projects register for accessibility review. A registration lists a building's size, estimated cost, and planned dates; it does not show that permits were issued or work was done. registration for 4650 FM 1694 lists a 657,130 ft² scope, an estimated cost of $399 million, and a September 2026 – November 2027 window. The company states the campus will use Closed-loop cooling: A cooling system that recirculates the same water instead of drawing new water continuously. cooling filled with water from outside Nueces County and that the design includes grid-support battery systems. Sourced · fair

In September 2026, Nueces County Commissioner Mike Pusley wrote that Hut 8 and economic-development representatives had told him and the County Judge the facility would use a closed-loop water system supplied from another state, with city water only for normal office use. He also wrote that the county has no zoning authority over the site and that the project is primarily sponsored by the Corpus Christi Economic Development Corporation. These are secondhand accounts of verbal assurances, not company documents. Sourced · weak

In October 2026, the chief of Nueces County ESD #1 (Annaville Fire Department) wrote that the district has fire jurisdiction of the area while the City of Corpus Christi Fire Marshal's Office reviews the fire code, including fire flow. He reported that responding crews are trained for lithium-ion battery fires, that the pre-plan covers extended monitoring for reignition, that the district has Mutual aid: An arrangement for neighboring fire departments to send help to each other when asked. with the Corpus Christi Fire Department and the Refinery Terminal Fire Company ( (Refinery Terminal Fire Company)RTFC (Refinery Terminal Fire Company): A private industrial fire-protection company based in Corpus Christi.), and that containment of fire-fighting runoff has not been addressed yet. In a follow-up, he wrote that the district has attended a multi-agency site-plan meeting for the construction phases, with more to come, and that cost recovery for an extended response has not been discussed (the district typically charges only for hazmat responses). These are the chief's brief written answers; plan contents and agreement terms are not public. Sourced · fair

Power and the grid

What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.

Loading grid records…

Published grid documents and the capacity comparison are in the interactive atlas, under Energy.

Who pays for the grid equipment

Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.

Filed grid projects

No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.

Who pays for this facility's connection

  • The data center or its developer (company statement). The company says it pre-funded the infrastructure costs required to serve its load; a trade report calls the payment a Contribution in aid of construction: A payment a customer makes to a utility to cover the cost of building the equipment that serves it.. Amount: UNKNOWN, not published. The company's account. No AEP Texas, ERCOT, or Public Utility Commission record of the payment was located, and the amount and what it covers are not published. Sourced · fairHut 8 Corp.Engineering News-Record

The rules · ERCOT, TX

New lines and transmission substations In force
Pays: Electricity users across the grid region. Equipment at 60 (kilovolt)kV (kilovolt): A measure of a power line's voltage. Higher-voltage lines, such as 138 kV or 345 kV, carry more power over longer distances. and above is paid for by electricity users across all of ERCOT, not only nearby. Each transmission utility's approved cost is shared among every distribution utility in ERCOT by its share of the summer peak. Sourced · strongPublic Utility Commission of Texas
On household bills In force
Pays: The utility's customers. Distribution utilities pass changes in those transmission charges on to their customers twice a year. Sourced · strongPublic Utility Commission of Texas
What a large data center pays itself In force
Pays: The data center or its developer. Texas (Senate Bill 6)SB 6 (Senate Bill 6): A state law setting rules for very large electricity users, including what they must pay toward their own grid connection. (2025) requires loads of 75 MW and up (the default threshold) to contribute to the utility's cost of connecting them, pay a screening study fee of at least $100,000, and post financial security for transmission built to serve them. Sourced · strongTexas Legislature
Proposed change Proposed
Pays: Electricity users across the grid region. In July 2026 the (Public Utility Commission of Texas)PUCT (Public Utility Commission of Texas): The state agency that regulates electric utilities, including the rules for who pays for grid equipment. proposed sharing transmission cost by 12 monthly peaks instead of 4 summer ones, with a minimum bill for large loads. Adoption is not confirmed. Sourced · strongPublic Utility Commission of Texas (Texas Register, July 24, 2026)
This facility's share
Unknown How much of any planned line or upgrade a single facility pays is not published; the rules above name no customer.

Hazards

Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.

What this facility's record says

Battery / (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. system
Batteries in design · type UNKNOWN
Sourced · fair
UPS configuration / chemistry
Not in the public record
Backup generation
Reported · installation, type, fuel, capacity UNKNOWN
Sourced · fair

Emergency response

The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.

Fire jurisdiction

Primary fire jurisdiction / first-due agency
Nueces County ESD #1 (Annaville FD) · per the district's fire chief
Sourced · fair

Fire and rescue stations (68)

NameStraight-line distanceRole
Annaville Volunteer Fire Department Station 1
Nueces County Emergency Services District #1
1.1 mi NNENearby origin
Corpus Christi Fire Department Station 2
Corpus Christi Fire Department
2.2 mi NWNearby origin
Corpus Christi Fire Department Station 12
Corpus Christi Fire Department
3.4 mi ESENearby origin
Annaville Fire Department
Nueces County Emergency Services District #1
3.8 mi SNearby origin
Nueces County ESD #1 (Annaville FD)
Nueces County Emergency Services District #1
4.0 mi SSWNearby origin
Annaville Fire Department Station 2
Nueces County Emergency Services District #1
4.9 mi WNWNearby origin
Robstown Fire Department5.0 mi SWNearby origin
Odem Volunteer Fire Department8.0 mi NNearby origin
Refinery Terminal Fire Company First Responders
Refinery Terminal Fire Company
8.7 mi ESENearby origin
Corpus Christi Fire Department Station 9
Corpus Christi Fire Department
9.4 mi ESENearby origin

The nearest 10 of 68. See all of them in the atlas →

Hospitals (19)

NameStraight-line distanceEmergency department
Corpus Christi Medical Center - Northwest Regional2.5 mi WNWNot in the public record
Corpus Christi Medical Center – Northwest3.9 mi NW24/7 ER
CHRISTUS Spohn Hospital Corpus Christi - Memorial12 mi ESENot in the public record
CHRISTUS Spohn Hospital Corpus Christi – Shoreline13 mi ESEYes
PAM Specialty Hospital of Corpus Christi North13 mi ESENot in the public record
CHRISTUS Dubuis Hospital of Corpus Christi13 mi ESENot in the public record
Corpus Christi Medical Center - Doctors Regional14 mi ESENot in the public record
Driscoll Children's Hospital14 mi ESENot in the public record
Corpus Christi Rehabilitation Hospital17 mi SENot in the public record
CHRISTUS Surgical Hospital17 mi SENot in the public record

The nearest 10 of 19. See all of them in the atlas →

Distances: Calculated · weak

Sources for these stations and hospitals (8)

Public bodies

The public offices, agencies, boards, and courts with a part in decisions about this data center: what each can decide, who it answers to, and where to ask for a record. A reference, not a scorecard.

What this record is missing

No public source yet for:

  • Local prevailing wind climatology (the cited severe-wind study does not establish it)
  • Battery chemistry, energy capacity, enclosure configuration, and UL 9540A test data
  • UPS configuration and backup generation (type, fuel, quantity)
  • Available fire flow (under City of Corpus Christi review), emergency access points, and fire-water runoff containment
  • Mutual-aid agreement terms
  • Substation / point of interconnection and transmission routing
  • Parcel boundary (only an approximate point is shown)

Changes (14)

  • 2026-11-15 New information Hut 8 Beacon Point: Added a "Who does what?" reference: the city, county, emergency, environmental, electricity, and project organizations around the campus, what each can decide, and where to ask for records. New records: city staff reviewed and recommended approval of a final plat naming Beacon Point DC LLC as owner (June 10, 2026 packet; the vote and recording are not verified), and the county listed a closed-session item on a proposed Beacon Point reinvestment zone on May 13, 2026. Source: City of Corpus Christi, Planning Commission; Nueces County Commissioners Court; Nueces County Commissioners Court.
  • 2026-11-14 New information Hut 8 Beacon Point: Company reports substation and Phase 1 foundation/underground utility work, with initial data-hall delivery targeted for Q3 2027 (Phase 1) and Q2 2028 (Phase 2). Source: Hut 8 Corp..
  • 2026-11-02 New information Hut 8 Beacon Point: Hut 8's SEC filings now confirm the campus substation is under construction on the site (previously a trade report only); its owner and voltage remain unpublished. Added the site's stormwater construction authorization and an ERCOT-accepted study of the Lon Hill area that modeled a code-named 1,000 MW load not linked to Beacon Point by any source. Source: Hut 8 Corp. (SEC EDGAR); Hut 8 Corp. (SEC EDGAR); U.S. Environmental Protection Agency (Facility Registry Service); ERCOT and AEP Service Corporation, filed at the PUCT.
  • 2026-10-28 Correction Hut 8 Beacon Point: Removed the sourced prevailing-wind default: the cited NWS page studies selected severe-wind events and does not establish prevailing wind climatology. Local prevailing wind is UNKNOWN; scenario wind remains an illustrative input. Previously: 135 degrees; NWS Corpus Christi prevailing SE. Source: National Weather Service, Corpus Christi (CRP).
  • 2026-10-12 New information Hut 8 Beacon Point: Recorded that the first 352 MW IT lease requires about 500 MW of utility capacity, and that Hut 8's release names AEP Texas as the party to the 1,000 MW interconnection agreement. Source: Hut 8 Corp. (via PR Newswire).
  • 2026-10-12 New information Hut 8 Beacon Point: Hut 8's project page says the company pre-funded the infrastructure costs required to serve its load; a trade report says substation construction has commenced. The amount paid and the substation's location remain unknown. Source: Hut 8 Corp.; Engineering News-Record.
  • 2026-10-12 New information Hut 8 Beacon Point: Added area grid context: ERCOT's April 2026 review found that a separate 1,150 MW load in Nueces County requires transmission upgrades. The county's existing supply capacity is not published, and ERCOT's project list does not name the station serving Beacon Point. Recorded the generating capacity located in the county: about 3,040 MW net summer. Source: Electric Reliability Council of Texas (ERCOT); Electric Reliability Council of Texas (ERCOT); U.S. Energy Information Administration.
  • 2026-10-07 New information Hut 8 Beacon Point: In a follow-up, the ESD #1 chief wrote that cost recovery for an extended response has not been discussed (the district typically charges only for hazmat responses) and that the district has attended a multi-agency site-plan meeting for the construction phases, with more planned. Source: Nueces County Emergency Services District #1 (Annaville Fire Department).
  • 2026-10-06 New information Hut 8 Beacon Point: The Nueces County ESD #1 (Annaville) fire chief wrote that the district has fire jurisdiction of the area while the City of Corpus Christi Fire Marshal's Office reviews the fire code, including fire flow. Previously: Primary fire jurisdiction UNKNOWN. Source: Nueces County Emergency Services District #1 (Annaville Fire Department).
  • 2026-10-06 New information Hut 8 Beacon Point: The chief reported battery-fire training for responding crews, a pre-plan covering reignition monitoring, and mutual aid with the Corpus Christi Fire Department and the Refinery Terminal Fire Company (RTFC); runoff containment has not been addressed yet. Source: Nueces County Emergency Services District #1 (Annaville Fire Department).
  • 2026-10-03 Project status Hut 8 Beacon Point: Corrected the stage to under construction: Hut 8's July release says construction had commenced. Previously: Under development · fully leased; PERMITTING. Source: Hut 8 Corp. (via PR Newswire).
  • 2026-10-03 New information Hut 8 Beacon Point: Commissioner Pusley said the county declined to offer Hut 8 a tax abatement; no formal decision record was located. Source: Corpus Christi Caller-Times (republished by AOL).
  • 2026-10-03 Correction Hut 8 Beacon Point: Hut 8's representative reported on-site backup generation for the project; installation, type, fuel, and capacity remain unknown. Previously: Backup generation (type, fuel, capacity) UNKNOWN. Source: KRIS 6 News.
  • 2026-09-23 Added to the atlas Hut 8 Beacon Point: Added to the atlas.

Related data centers

Others in Texas

Cite this record

"Hut 8 Beacon Point", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/hut8-beacon-point, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.

Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.