Key facts
Each value says what backs it, then how much weight it bears: Sourced (a cited source states it), Calculated (DCRA did the math, shown), or Unknown (not in the public record); then strong, fair, or weak. Weak labels are highlighted.
What the labels mean
- Sourced
- A cited source states it. Open the source to see who said it.
- Calculated
- DCRA calculated it from sourced values. The math is shown.
- Estimate
- An approximation where no source states the value.
- Modeled
- Output of an illustrative planning scenario. Not a forecast.
- Unknown
- Not in the public record. Unknown, not absent.
- Sourced · strong
- Strong: read directly in a primary record, such as a filing or the company's own release.
- Sourced · fair
- Fair: a company statement of its own plans, an official's written reply, or a solid report.
- Sourced · weak
- Highlighted. Weak: a secondhand account, a search excerpt, or a value that may be out of date.
The words are display only. The records and the dataset keep the original values (VERIFIED, DERIVED, ESTIMATED, MODELED, UNKNOWN; HIGH, MODERATE, LOW): Sourced is VERIFIED, Calculated is DERIVED, and strong, fair, and weak are HIGH, MODERATE, and LOW.
- Status
- Permitting · Shreveport permit appeal reported
- Calculated · fair
- Planned investment
- $18B · 3 campuses
- Sourced · fair
- Parishes
- Caddo and Bossier (incl. Resilient Technology Park, Shreveport)
- Sourced · fair
- Grid upgrades
- Amazon to fund SWEPCO energy infrastructure and grid upgrades
- Sourced · fair
- New Louisiana solar
- Up to 200 (megawatt)MW (megawatt): A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- Sourced · fair
"Not in the public record" means unknown, not absent. How DCRA sources and labels its records.
Plain-language glossary: 2 terms used on this page
- MW (megawatt)
- A measure of power at one moment. 1,000 MW is 1 GW (gigawatt). Energy used over time is measured in megawatt-hours (MWh).
- UPS (uninterruptible power supply)
- Batteries that keep computers running through the seconds between a power loss and backup generators starting.
Profile
Amazon's planned northwest Louisiana investment grew to $18 billion across three data center campuses in Caddo and Bossier parishes, including one at Resilient Technology Park in Shreveport, with up to 750 direct jobs. Amazon says it is funding SWEPCO grid upgrades and procuring up to 200 MW of new Louisiana solar. Sourced · fair
Power and the grid
What published records say about supplying this data center, and how its planned power compares in size with local demand today. A size comparison is not a grid study. Each label opens its sources.
Loading grid records…
Published grid documents and the capacity comparison are in the interactive atlas, under Energy.
Who pays for the grid equipment
Substations, lines, and transformers filed for this data center or its area, what each is filed to cost, and who the rules and documents say pays. Only filed or published documents are used; a cost with no document is unknown.
Filed grid projects
No filed substation, line, or transformer project is recorded for this facility yet. That means none has been researched or found, not that none exists.
Who pays for this facility's connection
Unknown No filed document or company statement recorded by DCRA says who paid, or will pay, for this facility's connection.
The rules
No cost rules are recorded for this region yet. DCRA adds a region's rules only after reading them in the regulator's or grid operator's own text.
Hazards
Materials a data center like this may hold, sorted by what is known about this one: confirmed at this facility, or only typical of the equipment and not confirmed here. A short reference, not a safety data sheet.
What this facility's record says
- Backup generation
- Not in the public record
Lithium-ion batteries
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Batteries may re-ignite after apparent extinguishment; extended monitoring is a planning consideration.
- Large volumes of water for cooling are frequently cited; the NIRS 2025 incident reported submersion of battery packs in water tanks.
- Site pre-plans, facility subject-matter experts, and installation documentation (NFPA 855, UL 9540A results) are the appropriate inputs for tactics.
Diesel fuel
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Foam and fuel-fire tactics apply to pool fires; tank quantity and containment design are UNKNOWN at Beacon Point.
Transformer insulating fluid
Associated with equipment category · not verified hereAssociated with the data-center equipment category; not verified at this facility. Unknown
Firefighting considerations and references
- Energized equipment: coordinate isolation with the utility before direct attack.
Emergency response
The fire department responsible for this site and the recorded fire stations and hospitals nearby, by straight-line distance from the approximate facility point. Not a dispatch order, response time, or first-due determination; mutual-aid roles are potential only. A capability missing from the public record is unknown, not absent.
Fire jurisdiction
- Primary fire jurisdiction
- Not in the public record
Fire and rescue stations (174)
| Name | Straight-line distance | Role |
|---|---|---|
| Bossier City Fire Department Station 2 | 0.8 mi SSW | Nearby origin |
| Bossier City Fire Department - Station 1 | 0.8 mi WNW | Nearby origin |
| Bossier City Fire Department - Station 3 | 1.4 mi NNW | Nearby origin |
| Bossier City Fire Department - Station 5 | 2.0 mi ENE | Nearby origin |
| Bossier City Fire Department - Station 6 | 2.0 mi W | Nearby origin |
| Shreveport Fire Department Station 5 | 2.1 mi SW | Nearby origin |
| Bossier City Fire Department - Station 4 | 3.2 mi SSE | Nearby origin |
| Shreveport Fire Department Central Station 1 | 3.5 mi W | Nearby origin |
| Shreveport Fire Department Station 7 | 3.6 mi SW | Nearby origin |
| Shreveport Fire Department Station 11 | 3.6 mi SSW | Nearby origin |
Hospitals (26)
| Name | Straight-line distance | Emergency department |
|---|---|---|
| Overton Brooks Veteran Affairs Medical Center | 1.7 mi SW | Not in the public record |
| Brentwood Hospital | 2.6 mi WSW | Not in the public record |
| Intensive Specialty Hospital of Louisiana | 2.7 mi NNW | Not in the public record |
| Willis Knighton Bossier Health Center | 2.9 mi NNW | Not in the public record |
| Specialists Hospital Shreveport | 3.1 mi WSW | Not in the public record |
| Intensive Specialty Hospital - Shreveport | 3.2 mi SW | Not in the public record |
| Ochsner LSU Health - Saint Mary Medical Center | 3.4 mi WSW | Not in the public record |
| Shriners Hospital Shreveport | 4.3 mi SW | Not in the public record |
| Ochsner LSU Health - Academic Medical Center | 4.5 mi SW | Not in the public record |
| Cornerstone Hospital - Bossier City | 4.5 mi SSE | Not in the public record |
Sources for these stations and hospitals (2)
What this record is missing
No public source yet for:
- Campus locations (one point stands in for three campuses)
- Power capacity (MW) and grid region
- Backup generation and battery/ (uninterruptible power supply)UPS (uninterruptible power supply): Batteries that keep computers running through the seconds between a power loss and backup generators starting. systems
- Local response resources not yet recorded
Changes (3)
- 2026-11-14 Project status Amazon Northwest Louisiana: Recorded reported Shreveport special-use permit appeal within the three-campus program; latest court disposition and building construction remain unconfirmed. Previously: Announced / planned; PROPOSED. Source: KTAL/KMSS via AOL. Public submission.
- 2026-11-14 New information Amazon Northwest Louisiana: Added SWEPCO's statement that the customer will fund project-specific substations and lines, and the parish's note that the Bossier site plan includes a new substation. Source: SWEPCO; Bossier Parish Police Jury.
- 2026-09-25 Added to the atlas Amazon Northwest Louisiana: Added to the atlas.
Related data centers
Others in Louisiana
Cite this record
"Amazon Northwest Louisiana", Data Center Risk Atlas, https://datacenterriskatlas.org/facilities/amazon-nw-louisiana, last checked Nov 14, 2026. Licensed under CC BY-NC 4.0.
Each record lists its own public sources. Cite those directly when a claim depends on them. See reuse and commercial licensing.