QTS Augusta

Data center campus · Richmond County, GA

QTS Data Centers

Status Permitting · site-plan review VERIFIED · MODERATE Stage: Permitting / approvals
Last checked against its sources Sep 30, 2026

Open in the interactive atlas →Company project page ↗

The atlas adds the map, nearby response resources, infrastructure dependencies, hazards, and illustrative planning scenarios for this site.

Profile

QTS describes a phased six-building campus in Augusta with the first building expected in spring 2028. The project is in site-plan review, and QTS says further approvals are required. Its proposed design includes closed-loop cooling and diesel emergency generators; QTS withholds power capacity and has not finalized generator details. VERIFIED · MODERATE

Key facts

Planned campus buildings
6
VERIFIED · MODERATE
First-building target
Spring 2028
VERIFIED · MODERATE
Planned cooling design
Closed-loop water system
VERIFIED · MODERATE
Planned emergency backup
Diesel generators
VERIFIED · MODERATE

VERIFIED values are stated by a cited source; DERIVED values are calculated from them; ESTIMATED values are approximations; UNKNOWN means no reliable public information, not absence. The map point is approximate and is not a parcel boundary.

Open questions

Changes (2)

Sources (4)

Planning and visualization only. DCRA is not a dispatch system, forecast, exposure or casualty model, or compliance determination. Scenarios in the atlas are hypothetical and do not predict what will happen at any facility.