{"manifest":{"name":"DCRA dataset (sample)","schema_version":"1.2","schema_changes":[{"version":"1.2","date":"2026-11-14","changes":["New table grid_projects: one row per filed grid project (substation, line, transformer, regional plan) listed for a facility, with its filed cost where a document states one and how the filing ties it to the facility.","New table cost_allocation: one row per statement or finding about who pays for a project or a facility's connection."]},{"version":"1.1","date":"2026-11-14","changes":["values: new column review (CHECKED or NOT_CHECKED). An empty grid value with NOT_CHECKED has not been researched yet; it is not a finding of UNKNOWN.","values: new column effective_date, filled on load_phase rows.","values: four new grid attributes on every facility: powerSupply, onsiteGeneration, curtailment, waterSource.","values: new groups queue (interconnection-queue and large-load request IDs) and load_phase (one row per dated step of the power ramp).","values: docket rows now carry attribute docket, permit, or planning_project, and their value_id ends in the filing number instead of a position, so it no longer changes when filings are reordered."]},{"version":"1.0","date":"2026-11-14","changes":["First layout."]}],"as_of":"2026-11-15","sample":true,"counts":{"facilities":1,"values":68,"sources":28,"changes":14,"grid_projects":0,"cost_allocation":1},"states":["TX"],"license":"https://creativecommons.org/licenses/by-nc/4.0/","rights":"© 2026 Data Center Risk Atlas. Records and text licensed under CC BY-NC 4.0 (https://creativecommons.org/licenses/by-nc/4.0/) with additional permissions for news reporting, public agencies, and research (datacenterriskatlas.org/terms#reuse). Reselling, redistributing, or building the records into a commercial product, dataset, API, or AI system requires a commercial license: licensing@datacenterriskatlas.org. Third-party material keeps its own terms.","attribution":"Data Center Risk Atlas (datacenterriskatlas.org), licensed under CC BY-NC 4.0","commercial_licensing":"licensing@datacenterriskatlas.org","note":"Reviewed public-record facts about new and proposed data centers. An empty value means UNKNOWN, except on rows marked NOT_CHECKED in the review column, which have not been researched yet. Planning information, not forecasts; DCRA does not model grid conditions.","columns":[{"table":"facilities","column":"facility_id","description":"Permanent DCRA identifier. Never reused or changed."},{"table":"facilities","column":"name","description":"Facility or project name as DCRA records it."},{"table":"facilities","column":"operator","description":"Developer, operator, and tenant as recorded."},{"table":"facilities","column":"state","description":"USPS state code."},{"table":"facilities","column":"county","description":"County, parish, or independent city."},{"table":"facilities","column":"county_fips","description":"5-digit county FIPS code."},{"table":"facilities","column":"latitude","description":"Reference point latitude (WGS 84)."},{"table":"facilities","column":"longitude","description":"Reference point longitude (WGS 84)."},{"table":"facilities","column":"location_evidence_class","description":"Evidence class of the reference point. ESTIMATED means an approximate planning point, not a parcel."},{"table":"facilities","column":"location_confidence","description":"Confidence in the reference point."},{"table":"facilities","column":"stage","description":"Project stage: PROPOSED, PERMITTING, UNDER_CONSTRUCTION, PARTLY_IN_SERVICE, IN_SERVICE, PAUSED, CANCELLED, or UNKNOWN."},{"table":"facilities","column":"monitoring_state","description":"ACTIVE while DCRA checks the record; ARCHIVED once frozen."},{"table":"facilities","column":"archived_since","description":"Date the record was archived; empty while active."},{"table":"facilities","column":"last_reviewed","description":"Date DCRA last checked the record, even if nothing changed."},{"table":"facilities","column":"last_changed","description":"Date of the newest recorded change; empty if none."},{"table":"facilities","column":"url","description":"The facility's page on the DCRA site."},{"table":"values","column":"value_id","description":"Permanent identifier of the value: facility, group, and attribute."},{"table":"values","column":"facility_id","description":"Facility the value belongs to."},{"table":"values","column":"group","description":"Part of the record: status, profile, grid, relationship, docket (regulatory dockets, permits, and grid planning projects), queue (interconnection-queue and large-load request IDs), or load_phase (one dated step of the power ramp). A grid row may repeat a profile row when the grid field is read from it."},{"table":"values","column":"attribute","description":"Machine name of the value, for example requestedLoad or voltageKv."},{"table":"values","column":"label","description":"Plain-language name of the value."},{"table":"values","column":"value","description":"The recorded value. Empty means UNKNOWN when review is CHECKED, and not yet researched when review is NOT_CHECKED; it is never a placeholder."},{"table":"values","column":"unit","description":"Unit of a numeric value, for example MW or kV."},{"table":"values","column":"display","description":"The value as the site shows it."},{"table":"values","column":"evidence_class","description":"VERIFIED, DERIVED, ESTIMATED, MODELED, or UNKNOWN."},{"table":"values","column":"confidence","description":"HIGH, MODERATE, LOW, or UNKNOWN."},{"table":"values","column":"support","description":"Strongest support among the sources: filed (a primary regulatory or government record), reported (a primary company or utility statement), estimated, or unverified (UNKNOWN, or secondary sources only)."},{"table":"values","column":"review","description":"CHECKED when the record states the value or records it as UNKNOWN after the sources were searched. NOT_CHECKED when nothing is recorded either way (grid rows only): the field has not been researched yet."},{"table":"values","column":"source_ids","description":"Sources cited for the value; join to the sources table."},{"table":"values","column":"source_urls","description":"Links to those sources, in the same order where a link exists."},{"table":"values","column":"checked","description":"Oldest access date among the value's sources."},{"table":"values","column":"observed_date","description":"Date the source observed or stated the value, when recorded."},{"table":"values","column":"effective_date","description":"When the value takes effect: a load phase's due date as the source gives it (YYYY, YYYY-MM, or YYYY-MM-DD). Empty on other rows or when the source gives no date."},{"table":"values","column":"methodology","description":"How a derived or estimated value was worked out."},{"table":"values","column":"notes","description":"Limits and context recorded with the value."},{"table":"sources","column":"source_id","description":"Permanent DCRA identifier of the source."},{"table":"sources","column":"title","description":"Title of the source document or page."},{"table":"sources","column":"publisher","description":"Who published it."},{"table":"sources","column":"url","description":"Link to the source; empty when it is not online."},{"table":"sources","column":"kind","description":"Type of source, for example REGULATORY_RECORD, COMPANY_DISCLOSURE, or LOCAL_REPORTING."},{"table":"sources","column":"primary","description":"true when the publisher is the originating party or record holder."},{"table":"sources","column":"published_date","description":"Publication date, when known."},{"table":"sources","column":"accessed_date","description":"Date DCRA last read the source."},{"table":"sources","column":"added_date","description":"Date the source entered DCRA's records."},{"table":"sources","column":"retrieval","description":"How it was read: DIRECT, SEARCH_EXCERPT, PACKAGE_DATASET, or OWNER_REVIEWED."},{"table":"changes","column":"date","description":"Date the change was recorded in DCRA."},{"table":"changes","column":"facility_id","description":"Facility the change concerns."},{"table":"changes","column":"kind","description":"ADDED, NEW_INFO, PERMIT_REGULATORY, STATUS_CHANGE, CORRECTION, ARCHIVED, or REACTIVATED."},{"table":"changes","column":"summary","description":"One plain sentence describing the change."},{"table":"changes","column":"attribute","description":"The value the change concerns, when it concerns one."},{"table":"changes","column":"previous","description":"The value shown before a correction or status change."},{"table":"changes","column":"source_ids","description":"Sources cited for the change."},{"table":"grid_projects","column":"project_row_id","description":"Permanent identifier: facility and DCRA project id."},{"table":"grid_projects","column":"facility_id","description":"Facility the project is listed for."},{"table":"grid_projects","column":"project_id","description":"The project's number in the filing body's own numbering."},{"table":"grid_projects","column":"id_scheme","description":"Whose numbering project_id is, for example ERCOT TPIT, ERCOT RPG, PJM RTEP, or MISO MTEP."},{"table":"grid_projects","column":"kind","description":"SUBSTATION, LINE, TRANSFORMER, TERMINAL, REGIONAL_PLAN, or OTHER."},{"table":"grid_projects","column":"name","description":"Plain name of the project, location first."},{"table":"grid_projects","column":"description","description":"What the filing says the project does."},{"table":"grid_projects","column":"owner","description":"Utility that owns or proposes it, as the filing names it."},{"table":"grid_projects","column":"status","description":"PROPOSED (not approved), PLANNED, UNDER_CONSTRUCTION, IN_SERVICE, or CANCELLED."},{"table":"grid_projects","column":"voltage_kv","description":"Voltage in kV, when the filing gives it."},{"table":"grid_projects","column":"capacity_mva","description":"Transformer capacity added, in MVA, when given."},{"table":"grid_projects","column":"new_circuit_miles","description":"New circuit miles, when given."},{"table":"grid_projects","column":"in_service_date","description":"In-service date, YYYY or YYYY-MM, when given."},{"table":"grid_projects","column":"in_service_basis","description":"ACTUAL when the filing reports the project in service; PROJECTED otherwise."},{"table":"grid_projects","column":"county","description":"County of the station or of the line's starting point."},{"table":"grid_projects","column":"filed_cost_usd","description":"The project's cost as a filed document states it, in US dollars. Empty means no filed document states one; it is never estimated."},{"table":"grid_projects","column":"cost_dollar_year","description":"The dollar year the document states for the cost."},{"table":"grid_projects","column":"attribution","description":"FACILITY_NAMED (the filing names the facility), DEVELOPER_NAMED (it names the facility's developer or its load), or AREA_SHARED (an area project naming neither). An AREA_SHARED cost is shared by many loads and is not the facility's cost."},{"table":"grid_projects","column":"attribution_note","description":"What is and is not known about the tie to the facility."},{"table":"grid_projects","column":"quote","description":"The filing's own words, short."},{"table":"grid_projects","column":"evidence_class","description":"VERIFIED, DERIVED, ESTIMATED, MODELED, or UNKNOWN."},{"table":"grid_projects","column":"confidence","description":"HIGH, MODERATE, LOW, or UNKNOWN."},{"table":"grid_projects","column":"source_ids","description":"Sources cited for the row; join to the sources table."},{"table":"grid_projects","column":"source_urls","description":"Links to those sources."},{"table":"grid_projects","column":"checked","description":"Date DCRA read the filing for this row."},{"table":"cost_allocation","column":"allocation_id","description":"Permanent identifier: facility and DCRA allocation id."},{"table":"cost_allocation","column":"facility_id","description":"Facility the row concerns."},{"table":"cost_allocation","column":"subject","description":"What is paid for: a grid_projects project_row_id suffix, or connection for the facility's own connection costs."},{"table":"cost_allocation","column":"payer","description":"FACILITY (the data center or its developer), UTILITY_CUSTOMERS, REGION_WIDE (electricity users across the grid region), or UNKNOWN."},{"table":"cost_allocation","column":"mechanism","description":"How the cost is collected, in plain words."},{"table":"cost_allocation","column":"amount_usd","description":"The amount a document states, in US dollars. Empty means none is published."},{"table":"cost_allocation","column":"basis","description":"Whose statement or finding this is, for example Company statement or Regulator order."},{"table":"cost_allocation","column":"evidence_class","description":"VERIFIED, DERIVED, ESTIMATED, MODELED, or UNKNOWN."},{"table":"cost_allocation","column":"confidence","description":"HIGH, MODERATE, LOW, or UNKNOWN."},{"table":"cost_allocation","column":"source_ids","description":"Sources cited for the row; join to the sources table."},{"table":"cost_allocation","column":"source_urls","description":"Links to those sources."},{"table":"cost_allocation","column":"notes","description":"Limits and context recorded with the row."}]},"facilities":[{"facility_id":"hut8-beacon-point","name":"Hut 8 Beacon Point","operator":"Hut 8 Corp.","state":"TX","county":"Nueces","county_fips":"48355","latitude":27.835,"longitude":-97.601,"location_evidence_class":"ESTIMATED","location_confidence":"LOW","stage":"UNDER_CONSTRUCTION","monitoring_state":"ACTIVE","archived_since":null,"last_reviewed":"2026-11-14","last_changed":"2026-11-15","url":"https://datacenterriskatlas.org/facilities/hut8-beacon-point"}],"values":[{"value_id":"hut8-beacon-point:status:status","facility_id":"hut8-beacon-point","group":"status","attribute":"status","label":"Status","value":"Construction commenced (company statement)","unit":null,"display":"Under construction · fully leased","evidence_class":"VERIFIED","confidence":"MODERATE","support":"filed","review":"CHECKED","source_ids":["hut8-pr-phase2","tdlr-tabs"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-fully-commercializes-1-gw-beacon-point-ai-data-center-campus-with-second-352-mw-it-lease-bringing-campus-level-base-term-contract-value-to-19-6-billion-302829514.html","https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Hut 8's July 2026 release says construction commenced and site preparation was underway. The November 4 update reports substation construction, Phase 1 foundation and underground utility work, and Phase 2 civil design. Physical progress is not independently verified."},{"value_id":"hut8-beacon-point:profile:data_hall_delivery_targets","facility_id":"hut8-beacon-point","group":"profile","attribute":"data_hall_delivery_targets","label":"Company data-hall delivery targets","value":"Phase 1 Q3 2027; Phase 2 Q2 2028","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["tx-hut8-q3-2026"],"source_urls":["https://www.hut8.com/news-insights/press-releases/hut-8-reports-third-quarter-2026-results"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"Initial data-hall delivery targets differ from initial energization and the TDLR registered-building completion schedule; none is a completed delivery."},{"value_id":"hut8-beacon-point:profile:utility_interconnection_capacity","facility_id":"hut8-beacon-point","group":"profile","attribute":"utility_interconnection_capacity","label":"Utility capacity","value":1000,"unit":"MW","display":"1,000 MW announced","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Executed interconnection agreement for 1 GW of utility capacity (company statement)."},{"value_id":"hut8-beacon-point:profile:campus_acreage","facility_id":"hut8-beacon-point","group":"profile","attribute":"campus_acreage","label":"Campus footprint","value":525,"unit":"acres","display":"525 acres announced","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-site"],"source_urls":["https://www.hut8.com/data-centers/beacon-point"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"Announced site area. No verified parcel boundary is drawn."},{"value_id":"hut8-beacon-point:profile:phase1_it_lease","facility_id":"hut8-beacon-point","group":"profile","attribute":"phase1_it_lease","label":"Phase 1 IT lease","value":352,"unit":"MW","display":"352 MW","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"15-year, triple-net lease; base-term contract value $9.8B."},{"value_id":"hut8-beacon-point:profile:phase1_utility_capacity","facility_id":"hut8-beacon-point","group":"profile","attribute":"phase1_utility_capacity","label":"Phase 1 utility capacity","value":500,"unit":"MW","display":"≈ 500 MW for the 352 MW IT lease","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"The company says the first 352 MW IT lease requires approximately 500 MW of utility capacity. The utility capacity needed for the second lease is not separately stated."},{"value_id":"hut8-beacon-point:profile:contracted_it_capacity","facility_id":"hut8-beacon-point","group":"profile","attribute":"contracted_it_capacity","label":"Contracted IT (2 leases)","value":704,"unit":"MW","display":"704 MW","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase2"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-fully-commercializes-1-gw-beacon-point-ai-data-center-campus-with-second-352-mw-it-lease-bringing-campus-level-base-term-contract-value-to-19-6-billion-302829514.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Second 352 MW, 15-year lease with the same tenant; campus base-term value $19.6B."},{"value_id":"hut8-beacon-point:profile:campus_contract_value","facility_id":"hut8-beacon-point","group":"profile","attribute":"campus_contract_value","label":"Campus base-term contract value","value":19.6,"unit":"USD billion","display":"$19.6 billion","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase2"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-fully-commercializes-1-gw-beacon-point-ai-data-center-campus-with-second-352-mw-it-lease-bringing-campus-level-base-term-contract-value-to-19-6-billion-302829514.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:workload","facility_id":"hut8-beacon-point","group":"profile","attribute":"workload","label":"Intended workload","value":"AI training and inference","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:tenant","facility_id":"hut8-beacon-point","group":"profile","attribute":"tenant","label":"Tenant","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Described only as a high-investment-grade tenant. Secondary reports naming a tenant are unconfirmed."},{"value_id":"hut8-beacon-point:profile:initial_energization","facility_id":"hut8-beacon-point","group":"profile","attribute":"initial_energization","label":"Initial energization (target)","value":"2027-Q1","unit":null,"display":"Q1 2027 target","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1","hut8-q2-2026"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html","https://www.sec.gov/Archives/edgar/data/1964789/000110465926090041/tm2621890d1_ex99-1.htm"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Company target. ERCOT large-load review status per management statements only."},{"value_id":"hut8-beacon-point:profile:data_hall_delivery","facility_id":"hut8-beacon-point","group":"profile","attribute":"data_hall_delivery","label":"Preliminary data hall delivery (target)","value":"2027-Q3","unit":null,"display":"Q3 2027 target","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:filed_building_area","facility_id":"hut8-beacon-point","group":"profile","attribute":"filed_building_area","label":"Filed building scope","value":657130,"unit":"ft²","display":"657,130 ft²","evidence_class":"VERIFIED","confidence":"MODERATE","support":"filed","review":"CHECKED","source_ids":["tdlr-tabs","connectcre-tdlr"],"source_urls":["https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611","https://www.connectcre.com/stories/data-center-operator-to-begin-work-on-399m-corpus-christi-campus/"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"TDLR TABS2027000611 filing, rechecked directly on 2026-10-03."},{"value_id":"hut8-beacon-point:profile:filed_estimated_cost","facility_id":"hut8-beacon-point","group":"profile","attribute":"filed_estimated_cost","label":"Filed estimated cost (registered scope)","value":399,"unit":"USD million","display":"$399 million","evidence_class":"VERIFIED","confidence":"MODERATE","support":"filed","review":"CHECKED","source_ids":["tdlr-tabs","connectcre-tdlr"],"source_urls":["https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611","https://www.connectcre.com/stories/data-center-operator-to-begin-work-on-399m-corpus-christi-campus/"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Applies to the TDLR-registered scope, not total campus investment."},{"value_id":"hut8-beacon-point:profile:filed_schedule","facility_id":"hut8-beacon-point","group":"profile","attribute":"filed_schedule","label":"Filed construction window","value":"2026-09/2027-11","unit":null,"display":"Sep 2026 – Nov 2027","evidence_class":"VERIFIED","confidence":"MODERATE","support":"filed","review":"CHECKED","source_ids":["tdlr-tabs","connectcre-tdlr"],"source_urls":["https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611","https://www.connectcre.com/stories/data-center-operator-to-begin-work-on-399m-corpus-christi-campus/"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:design_firm","facility_id":"hut8-beacon-point","group":"profile","attribute":"design_firm","label":"Design firm (filed)","value":"Jacobs Project Management Co.","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"filed","review":"CHECKED","source_ids":["tdlr-tabs","connectcre-tdlr"],"source_urls":["https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611","https://www.connectcre.com/stories/data-center-operator-to-begin-work-on-399m-corpus-christi-campus/"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:construction_financing","facility_id":"hut8-beacon-point","group":"profile","attribute":"construction_financing","label":"Construction financing (reported)","value":4.25,"unit":"USD billion","display":"$4.25 billion","evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["constructionfront-financing"],"source_urls":["https://constructionfront.com/2026-06-12-hut-8-closes-us4-25-billion-construction-financing-for-beacon-point-data-center-in-texas/"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"Secondary report."},{"value_id":"hut8-beacon-point:profile:jurisdiction","facility_id":"hut8-beacon-point","group":"profile","attribute":"jurisdiction","label":"Local jurisdiction","value":"Unincorporated Nueces County","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["coastal-bend-current-oversight"],"source_urls":["https://www.coastalbendcurrent.com/blogs/beacon-point-moves-ahead-without-any-local-oversight"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Reported as outside Robstown and Corpus Christi city limits. Confirm with county records."},{"value_id":"hut8-beacon-point:profile:cooling","facility_id":"hut8-beacon-point","group":"profile","attribute":"cooling","label":"Cooling approach","value":"Closed loop","unit":null,"display":"Closed-loop (company statement)","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-pr-responsible"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-affirms-commitment-to-responsible-data-center-development-following-directive-from-texas-governor-greg-abbott-302847136.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Filled once with water sourced from outside Nueces County; expected to remain in use ~4–7 years. Design intent, not operating data."},{"value_id":"hut8-beacon-point:profile:battery_systems","facility_id":"hut8-beacon-point","group":"profile","attribute":"battery_systems","label":"Battery / UPS system","value":"Grid-support batteries in design","unit":null,"display":"Batteries in design · type UNKNOWN","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-pr-responsible"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-affirms-commitment-to-responsible-data-center-development-following-directive-from-texas-governor-greg-abbott-302847136.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Company states the design incorporates battery systems to mitigate voltage impacts. Chemistry, energy capacity, location, UPS configuration, and protection design are UNKNOWN."},{"value_id":"hut8-beacon-point:profile:ups_configuration","facility_id":"hut8-beacon-point","group":"profile","attribute":"ups_configuration","label":"UPS configuration / chemistry","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:backup_generation","facility_id":"hut8-beacon-point","group":"profile","attribute":"backup_generation","label":"Backup generation","value":"Company representative reports on-site backup generation for project","unit":null,"display":"Reported · installation, type, fuel, capacity UNKNOWN","evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["kristv-beacon-point"],"source_urls":["https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"Hut 8's senior director of regulatory and government affairs told KRIS the project has backup generation on site. Installation status, generator type, fuel, quantity, and capacity were not independently established."},{"value_id":"hut8-beacon-point:profile:fuel_storage","facility_id":"hut8-beacon-point","group":"profile","attribute":"fuel_storage","label":"On-site fuel storage","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:fire_code_review","facility_id":"hut8-beacon-point","group":"profile","attribute":"fire_code_review","label":"Fire-code review","value":"City of Corpus Christi Fire Marshal's Office (in progress)","unit":null,"display":"Corpus Christi Fire Marshal's Office · in progress (per ESD #1 chief)","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"Reported by the ESD #1 chief, including that fire flow is under this review. Which code edition applies, the basis for the city's review of an unincorporated site, and the review's findings are UNKNOWN."},{"value_id":"hut8-beacon-point:profile:pre_incident_plan","facility_id":"hut8-beacon-point","group":"profile","attribute":"pre_incident_plan","label":"Site-plan review / pre-incident plan","value":"Multi-agency site-plan meeting held for the construction phases, more planned; pre-plan covers extended monitoring for battery reignition (as reported)","unit":null,"display":"Site-plan meeting held · more planned · contents UNKNOWN","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06","ncesd1-clack-email-2026-10-07"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The chief answered \"Yes\" to whether the pre-plan covers extended on-scene monitoring for reignition. Asked whether the site-plan review was complete, he wrote that the district has sat through a site-plan meeting with multiple agencies for the construction phases and will have more meetings as they progress. The agencies, dates, and pre-plan contents are not stated."},{"value_id":"hut8-beacon-point:profile:extended_response_cost_recovery","facility_id":"hut8-beacon-point","group":"profile","attribute":"extended_response_cost_recovery","label":"Cost recovery for an extended response","value":"Not discussed; the district typically charges only for hazmat responses (per ESD #1 chief)","unit":null,"display":"Not discussed · as of Oct 7, 2026","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-07"],"source_urls":[],"checked":"2026-10-07","observed_date":null,"effective_date":null,"methodology":null,"notes":"The chief wrote that no cost recovery has been discussed, with Hut 8 or through mutual aid, and that the district typically charges only for hazmat responses. This records the status at the time of the reply; it is not a finding about any obligation."},{"value_id":"hut8-beacon-point:profile:responder_battery_training","facility_id":"hut8-beacon-point","group":"profile","attribute":"responder_battery_training","label":"Responder lithium-ion battery training","value":"Responding crews trained for lithium-ion battery fires (as reported)","unit":null,"display":"Reported yes · extent UNKNOWN","evidence_class":"VERIFIED","confidence":"LOW","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The ESD #1 chief answered yes. Course, hours, certification, and which mutual-aid crews are included are not stated."},{"value_id":"hut8-beacon-point:profile:mutual_aid","facility_id":"hut8-beacon-point","group":"profile","attribute":"mutual_aid","label":"Mutual aid (first-due district)","value":"ESD #1 has mutual aid with Corpus Christi Fire Department and Refinery Terminal Fire Company (RTFC)","unit":null,"display":"Corpus Christi FD and Refinery Terminal Fire Co. (per ESD #1 chief)","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06","rtfc-site"],"source_urls":["https://www.rtfc.org/"],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The chief wrote \"RTFC\"; DCRA reads it as the Refinery Terminal Fire Company, a private industrial fire-protection company based in Corpus Christi (per its website, which does not mention this agreement). Agreement terms and resources covered (relief crews, tenders, hazmat) are UNKNOWN. Cost recovery is recorded separately."},{"value_id":"hut8-beacon-point:profile:fire_water_supply","facility_id":"hut8-beacon-point","group":"profile","attribute":"fire_water_supply","label":"Fire-suppression water supply","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"Provider, main size, storage, and available fire flow are not public. The ESD #1 chief reports fire flow is being reviewed by the City of Corpus Christi Fire Marshal's Office. The cooling disclosure does not address fire flow."},{"value_id":"hut8-beacon-point:profile:runoff_containment","facility_id":"hut8-beacon-point","group":"profile","attribute":"runoff_containment","label":"Fire-fighting water runoff containment","value":"Not yet addressed (per ESD #1 chief, Oct 2026)","unit":null,"display":"Not yet addressed · as of Oct 6, 2026","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The chief wrote that containment of fire-fighting runoff has not been addressed yet. This records planning status at the time of the reply; it is not a finding that any rule applies or is unmet. Drainage paths and receiving waters remain unmapped in DCRA."},{"value_id":"hut8-beacon-point:profile:potable_water","facility_id":"hut8-beacon-point","group":"profile","attribute":"potable_water","label":"Domestic / potable water provider","value":"City water for normal office use only (as reported)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"LOW","support":"reported","review":"CHECKED","source_ids":["nueces-pusley-email-2026-09-25"],"source_urls":[],"checked":"2026-09-26","observed_date":null,"effective_date":null,"methodology":null,"notes":"A county commissioner reports that Hut 8 and economic-development representatives told county officials the only water needed from the city is for normal office use. The provider is not named beyond \"the city\", volumes are UNKNOWN, and this is not a company document."},{"value_id":"hut8-beacon-point:profile:water_assurance_county","facility_id":"hut8-beacon-point","group":"profile","attribute":"water_assurance_county","label":"Water assurances reported by county officials","value":"Closed-loop cooling; facility water from another state; city water for office use only","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"LOW","support":"reported","review":"CHECKED","source_ids":["nueces-pusley-email-2026-09-25"],"source_urls":[],"checked":"2026-09-26","observed_date":null,"effective_date":null,"methodology":null,"notes":"Secondhand account (Sept. 2026) of verbal assurances at a meeting with the County Judge and a commissioner. The company's own statement says cooling water comes from outside Nueces County; \"another state\" is more specific and is not confirmed by a company document."},{"value_id":"hut8-beacon-point:profile:economic_development_sponsor","facility_id":"hut8-beacon-point","group":"profile","attribute":"economic_development_sponsor","label":"Local economic-development sponsor","value":"Corpus Christi Economic Development Corporation (as reported)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"LOW","support":"reported","review":"CHECKED","source_ids":["nueces-pusley-email-2026-09-25"],"source_urls":[],"checked":"2026-09-26","observed_date":null,"effective_date":null,"methodology":null,"notes":"The commissioner describes the project as \"primarily being sponsored\" by this organization. The nature of the sponsorship (incentives, agreements) is UNKNOWN."},{"value_id":"hut8-beacon-point:profile:county_land_use_authority","facility_id":"hut8-beacon-point","group":"profile","attribute":"county_land_use_authority","label":"County land-use authority","value":"No county zoning or general land-use regulation; subdivision rules only (per commissioner)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"LOW","support":"reported","review":"CHECKED","source_ids":["nueces-pusley-email-2026-09-25"],"source_urls":[],"checked":"2026-09-26","observed_date":null,"effective_date":null,"methodology":null,"notes":"The commissioner's description of Texas county authority (no home-rule zoning). The statutory basis is not yet cited."},{"value_id":"hut8-beacon-point:profile:county_tax_abatement","facility_id":"hut8-beacon-point","group":"profile","attribute":"county_tax_abatement","label":"County tax abatement position","value":"Commissioner says the county declined to offer Hut 8 an abatement","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["caller-times-nueces-address-2026-10-02"],"source_urls":["https://www.aol.com/articles/nueces-county-address-covers-finances-153610000.html"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"Caller-Times report of Commissioner Mike Pusley's October 1 statement. No formal county decision record or application was located; this records his statement, not an independently verified court action."},{"value_id":"hut8-beacon-point:profile:grid_infrastructure_funding","facility_id":"hut8-beacon-point","group":"profile","attribute":"grid_infrastructure_funding","label":"Grid infrastructure costs (company statement)","value":"Company says it pre-funded the infrastructure costs required to serve its load","unit":null,"display":"Pre-funded by Hut 8 (company statement) · amount UNKNOWN","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-site","enr-jacobs-beacon-point"],"source_urls":["https://www.hut8.com/data-centers/beacon-point","https://www.enr.com/articles/63004-jacobs-expands-epcm-role-with-hut-8s-1-gw-texas-ai-campus"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"Hut 8's project page says these costs will not be passed on to residential customers and that the project is not expected to raise residential bills. This is the company's account; no AEP Texas, ERCOT, or Public Utility Commission record of the payment or cost allocation was located. The amount and what it covers are not published. A trade report describes the payment as funded contribution-in-aid-of-construction requirements."},{"value_id":"hut8-beacon-point:profile:substation_construction","facility_id":"hut8-beacon-point","group":"profile","attribute":"substation_construction","label":"Substation construction","value":"Under construction on the campus (company filings)","unit":null,"display":"Under construction on campus · owner, voltage UNKNOWN","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-q2-2026","hut8-8k-notes-2026-06","enr-jacobs-beacon-point"],"source_urls":["https://www.sec.gov/Archives/edgar/data/1964789/000110465926090041/tm2621890d1_ex99-1.htm","https://www.sec.gov/Archives/edgar/data/1964789/000110465926070744/tm2616926d1_ex99-1.htm","https://www.enr.com/articles/63004-jacobs-expands-epcm-role-with-hut-8s-1-gw-texas-ai-campus"],"checked":"2026-11-02","observed_date":null,"effective_date":null,"methodology":null,"notes":"Hut 8's Q2 2026 results say construction of the campus substation is under way, and its June 2026 notes filing funds the substation located on the property. These are company statements; no AEP Texas or ERCOT record of the substation was found. Its owner, voltage, and the utility station it ties into are not public. Engineering News-Record first reported the start in May 2026."},{"value_id":"hut8-beacon-point:profile:stormwater_permit","facility_id":"hut8-beacon-point","group":"profile","attribute":"stormwater_permit","label":"Stormwater construction authorization","value":"TXR1553YP","unit":null,"display":"TXR1553YP (construction stormwater)","evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["epa-frs-beacon-point"],"source_urls":["https://frs-public.epa.gov/ords/frs_public2/fii_query_dtl.disp_program_facility?p_registry_id=110072227954"],"checked":"2026-11-02","observed_date":null,"effective_date":null,"methodology":null,"notes":"Listed in EPA's Facility Registry Service for the Beacon Point Data Center Project, 4650 FM Rd 1694, Robstown. TCEQ issues the authorization; EPA's registry aggregates it. No air permit appears in the registry entry."},{"value_id":"hut8-beacon-point:profile:point_of_interconnection","facility_id":"hut8-beacon-point","group":"profile","attribute":"point_of_interconnection","label":"Substation / point of interconnection","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":["ercot-tpit-2026-07"],"source_urls":["https://www.ercot.com/files/docs/2022/03/02/ERCOT-July-Ad-Hoc-TPIT-No-Cost-071326-UPDATE.xlsx"],"checked":"2026-10-12","observed_date":null,"effective_date":null,"methodology":null,"notes":"Substation location, owner, voltage, and the lines serving it are not public in the sources read. ERCOT's July 2026 transmission project list names no Hut 8 or Beacon Point project. It does list AEP load interconnections in Nueces County under code names, including a new 345 kV terminal at the Lon Hill station for the \"Tom Cruise load\" (projected in service March 2027). DCRA has not matched any code name to this campus and draws no line."},{"value_id":"hut8-beacon-point:profile:county_supply_capacity","facility_id":"hut8-beacon-point","group":"profile","attribute":"county_supply_capacity","label":"Existing peak electric supply capacity, Nueces County","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":["ercot-eir-25rpg016"],"source_urls":["https://www.ercot.com/files/docs/2026/04/13/5.2-25RPG016-STEC-Nueces-Green-Ammonia-Load-Interconnection-Project.pdf"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"No public source states how much load the grid can serve in Nueces County today. ERCOT reports load by weather zone, and Nueces County is one part of its South Weather Zone. Supply depends on both local generation and transmission into the area, and ERCOT's study case data is not public. Generating capacity located in the county is recorded separately and is only one part of supply."},{"value_id":"hut8-beacon-point:profile:county_generation_capacity","facility_id":"hut8-beacon-point","group":"profile","attribute":"county_generation_capacity","label":"Generating capacity located in Nueces County","value":3040,"unit":"MW","display":"≈ 3,040 MW net summer (39 generators, Aug 2026)","evidence_class":"DERIVED","confidence":"HIGH","support":"filed","review":"CHECKED","source_ids":["eia-860m-2026-08"],"source_urls":["https://www.eia.gov/electricity/data/eia860m/xls/august_generator2026.xlsx"],"checked":"2026-10-12","observed_date":null,"effective_date":null,"methodology":"Sum of net summer capacity for every operating generator EIA lists in Nueces County, Texas (3,040.1 MW; nameplate 3,407.5 MW).","notes":"About 2,168 MW is natural gas, 475 MW wind, 305 MW batteries, and 93 MW other. This is installed capacity inside the county, not power reserved for it: the plants sell into the ERCOT grid, wind and battery output varies, and about 190 MW sits at industrial sites that mainly serve themselves. It is not the county's supply limit and is not a comparison with Beacon Point's draw."},{"value_id":"hut8-beacon-point:profile:area_transmission_study","facility_id":"hut8-beacon-point","group":"profile","attribute":"area_transmission_study","label":"ERCOT transmission study, Nueces County (separate project)","value":"A separate 1,150 MW load in Nueces County produced overloads and unsolved cases in ERCOT's 2029 summer-peak study","unit":null,"display":"ERCOT found upgrades needed for a separate 1,150 MW load (April 2026)","evidence_class":"VERIFIED","confidence":"HIGH","support":"filed","review":"CHECKED","source_ids":["ercot-eir-25rpg016"],"source_urls":["https://www.ercot.com/files/docs/2026/04/13/5.2-25RPG016-STEC-Nueces-Green-Ammonia-Load-Interconnection-Project.pdf"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"ERCOT staff reviewed a cooperative's request to connect a 1,150 MW ammonia-plant load in 2028. With that load added, single-outage tests overloaded the Lon Hill to Calallen 69 kV and Lon Hill to Bunsen 138 kV lines and two cases did not solve. Staff recommended a $161.1 million project for May 2031 and estimated it adds about 633 MW of further load-serving capability in the county. The report does not mention Beacon Point or say whether its load is in the study case, so this is context for the area, not a finding about this campus."},{"value_id":"hut8-beacon-point:profile:communications","facility_id":"hut8-beacon-point","group":"profile","attribute":"communications","label":"Fiber / communications providers","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:profile:parcel_boundary","facility_id":"hut8-beacon-point","group":"profile","attribute":"parcel_boundary","label":"Parcel boundary","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":"No verified parcel geometry recorded."},{"value_id":"hut8-beacon-point:profile:fire_jurisdiction","facility_id":"hut8-beacon-point","group":"profile","attribute":"fire_jurisdiction","label":"Primary fire jurisdiction / first-due agency","value":"Nueces County Emergency Services District #1 (Annaville Fire Department)","unit":null,"display":"Nueces County ESD #1 (Annaville FD) · per the district's fire chief","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The district's chief wrote that ESD #1 has jurisdiction of the area while the City of Corpus Christi reviews the fire code, and answered yes when asked whether first-due responsibility is settled among area departments. Station locations, response routes, and travel times are not established. NERIS boundaries at the map point: Nueces County Emergency Services District #1; Agua Dulce Volunteer Fire Department; Corpus Christi Fire Department. More than one NERIS boundary contains the map point."},{"value_id":"hut8-beacon-point:grid:gridOperator","facility_id":"hut8-beacon-point","group":"grid","attribute":"gridOperator","label":"Grid operator","value":"ERCOT","unit":null,"display":"ERCOT","evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["needham-ercot-review","kristv-beacon-point"],"source_urls":["https://finance.yahoo.com/technology/ai/articles/hut-8-says-beacon-point-132234125.html","https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Management states the project is in ERCOT large-load review with Q1 2027 energization targeted."},{"value_id":"hut8-beacon-point:grid:zone","facility_id":"hut8-beacon-point","group":"grid","attribute":"zone","label":"Grid load zone","value":"Southern","unit":null,"display":"ERCOT Southern weather zone","evidence_class":"DERIVED","confidence":"HIGH","support":"filed","review":"CHECKED","source_ids":["ercot-eir-25rpg016","tdlr-tabs"],"source_urls":["https://www.ercot.com/files/docs/2026/04/13/5.2-25RPG016-STEC-Nueces-Green-Ammonia-Load-Interconnection-Project.pdf","https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":"The campus's filed address is in Nueces County (TDLR); ERCOT's independent review 25RPG016 places Nueces County in the Southern weather zone.","notes":"Weather zones are the smallest ERCOT area with published hourly load. The zone covers many counties; it is not the campus's supply area."},{"value_id":"hut8-beacon-point:grid:utility","facility_id":"hut8-beacon-point","group":"grid","attribute":"utility","label":"Serving utility","value":"AEP Texas","unit":null,"display":"AEP Texas","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1","kristv-beacon-point"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html","https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Hut 8 states that it and AEP Texas executed an interconnection agreement for 1,000 MW of utility capacity (company release). Large loads proceed through ERCOT review. Substation, point of interconnection, and line routing are UNKNOWN. No line is drawn."},{"value_id":"hut8-beacon-point:grid:transmissionOwner","facility_id":"hut8-beacon-point","group":"grid","attribute":"transmissionOwner","label":"Transmission owner","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"NOT_CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:grid:pointOfInterconnection","facility_id":"hut8-beacon-point","group":"grid","attribute":"pointOfInterconnection","label":"Substation / point of interconnection","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":["ercot-tpit-2026-07"],"source_urls":["https://www.ercot.com/files/docs/2022/03/02/ERCOT-July-Ad-Hoc-TPIT-No-Cost-071326-UPDATE.xlsx"],"checked":"2026-10-12","observed_date":null,"effective_date":null,"methodology":null,"notes":"Substation location, owner, voltage, and the lines serving it are not public in the sources read. ERCOT's July 2026 transmission project list names no Hut 8 or Beacon Point project. It does list AEP load interconnections in Nueces County under code names, including a new 345 kV terminal at the Lon Hill station for the \"Tom Cruise load\" (projected in service March 2027). DCRA has not matched any code name to this campus and draws no line."},{"value_id":"hut8-beacon-point:grid:voltageKv","facility_id":"hut8-beacon-point","group":"grid","attribute":"voltageKv","label":"Interconnection voltage","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"NOT_CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:grid:requestedLoad","facility_id":"hut8-beacon-point","group":"grid","attribute":"requestedLoad","label":"Power requested or agreed","value":1000,"unit":"MW","display":"1,000 MW announced","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Executed interconnection agreement for 1 GW of utility capacity (company statement)."},{"value_id":"hut8-beacon-point:grid:firstPhaseLoad","facility_id":"hut8-beacon-point","group":"grid","attribute":"firstPhaseLoad","label":"First-phase power","value":500,"unit":"MW","display":"≈ 500 MW for the 352 MW IT lease","evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"The company says the first 352 MW IT lease requires approximately 500 MW of utility capacity. The utility capacity needed for the second lease is not separately stated."},{"value_id":"hut8-beacon-point:grid:loadSchedule","facility_id":"hut8-beacon-point","group":"grid","attribute":"loadSchedule","label":"Power ramp schedule","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"NOT_CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:grid:powerSupply","facility_id":"hut8-beacon-point","group":"grid","attribute":"powerSupply","label":"Power supply","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"NOT_CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:grid:onsiteGeneration","facility_id":"hut8-beacon-point","group":"grid","attribute":"onsiteGeneration","label":"On-site generation","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"NOT_CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:grid:curtailment","facility_id":"hut8-beacon-point","group":"grid","attribute":"curtailment","label":"Curtailment commitment","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"NOT_CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":null},{"value_id":"hut8-beacon-point:grid:waterSource","facility_id":"hut8-beacon-point","group":"grid","attribute":"waterSource","label":"Water source","value":"Cooling loop filled once with water from outside Nueces County","unit":null,"display":"Outside Nueces County, one-time cooling fill (company) · supplier UNKNOWN","evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-pr-responsible"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-affirms-commitment-to-responsible-data-center-development-following-directive-from-texas-governor-greg-abbott-302847136.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Company statement of design intent, not operating data: a closed-loop system filled once, with no ongoing draw from local sources for cooling. The supplier and the volume are not named. The provider of domestic and fire-flow water is UNKNOWN (see the potable water and fire-flow entries)."},{"value_id":"hut8-beacon-point:relationship:power_transmission_distribution_utility","facility_id":"hut8-beacon-point","group":"relationship","attribute":"power_transmission_distribution_utility","label":"Transmission / distribution utility","value":"AEP Texas","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"HIGH","support":"reported","review":"CHECKED","source_ids":["hut8-pr-phase1","kristv-beacon-point"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html","https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Hut 8 states that it and AEP Texas executed an interconnection agreement for 1,000 MW of utility capacity (company release). Large loads proceed through ERCOT review. Substation, point of interconnection, and line routing are UNKNOWN. No line is drawn. Route: UNKNOWN."},{"value_id":"hut8-beacon-point:relationship:power_grid_region","facility_id":"hut8-beacon-point","group":"relationship","attribute":"power_grid_region","label":"Grid region","value":"ERCOT","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["needham-ercot-review","kristv-beacon-point"],"source_urls":["https://finance.yahoo.com/technology/ai/articles/hut-8-says-beacon-point-132234125.html","https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Management states the project is in ERCOT large-load review with Q1 2027 energization targeted. Route: LOGICAL_ONLY."},{"value_id":"hut8-beacon-point:relationship:backup_power_grid_support_batteries","facility_id":"hut8-beacon-point","group":"relationship","attribute":"backup_power_grid_support_batteries","label":"Grid-support batteries","value":"On-site (design)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-pr-responsible"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-affirms-commitment-to-responsible-data-center-development-following-directive-from-texas-governor-greg-abbott-302847136.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Design incorporates battery systems to mitigate voltage impacts (company). Type and capacity UNKNOWN. Route: UNKNOWN."},{"value_id":"hut8-beacon-point:relationship:backup_power_backup_generation","facility_id":"hut8-beacon-point","group":"relationship","attribute":"backup_power_backup_generation","label":"Backup generation","value":null,"unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"unverified","review":"CHECKED","source_ids":["kristv-beacon-point"],"source_urls":["https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county"],"checked":"2026-11-14","observed_date":null,"effective_date":null,"methodology":null,"notes":"A Hut 8 representative reported on-site backup generation for the project; installation status, type, fuel, and capacity remain UNKNOWN. Route: UNKNOWN."},{"value_id":"hut8-beacon-point:relationship:water_cooling_water","facility_id":"hut8-beacon-point","group":"relationship","attribute":"water_cooling_water","label":"Cooling water","value":"Outside Nueces County (unnamed)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["hut8-pr-responsible"],"source_urls":["https://www.prnewswire.com/news-releases/hut-8-affirms-commitment-to-responsible-data-center-development-following-directive-from-texas-governor-greg-abbott-302847136.html"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Closed-loop system filled once with water sourced from outside Nueces County; company states no ongoing draw from local sources for cooling. No connection to O.N. Stevens WTP or any City of Corpus Christi facility is asserted. Route: LOGICAL_ONLY."},{"value_id":"hut8-beacon-point:relationship:water_fire_flow_domestic_water","facility_id":"hut8-beacon-point","group":"relationship","attribute":"water_fire_flow_domestic_water","label":"Fire-flow / domestic water","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"Provider, main size, storage, and available fire flow are not publicly established. The ESD #1 chief reports fire flow is under review by the City of Corpus Christi Fire Marshal's Office. Route: UNKNOWN."},{"value_id":"hut8-beacon-point:relationship:emergency_fire_jurisdiction","facility_id":"hut8-beacon-point","group":"relationship","attribute":"emergency_fire_jurisdiction","label":"Fire jurisdiction","value":"Nueces County ESD #1 (Annaville FD)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06"],"source_urls":[],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The district's chief reports ESD #1 has jurisdiction of the area while the City of Corpus Christi reviews the fire code. Response routes and travel times are not established. No route is drawn. Route: UNKNOWN."},{"value_id":"hut8-beacon-point:relationship:emergency_mutual_aid","facility_id":"hut8-beacon-point","group":"relationship","attribute":"emergency_mutual_aid","label":"Mutual aid","value":"Corpus Christi Fire Department; Refinery Terminal Fire Company (RTFC)","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"reported","review":"CHECKED","source_ids":["ncesd1-clack-email-2026-10-06","rtfc-site"],"source_urls":["https://www.rtfc.org/"],"checked":"2026-10-06","observed_date":null,"effective_date":null,"methodology":null,"notes":"The ESD #1 chief reports mutual aid with the Corpus Christi Fire Department and Refinery Terminal Fire Company (RTFC). Agreement terms are UNKNOWN; the chief reports cost recovery for an extended response has not been discussed. Route: LOGICAL_ONLY."},{"value_id":"hut8-beacon-point:relationship:communications_fiber_communications","facility_id":"hut8-beacon-point","group":"relationship","attribute":"communications_fiber_communications","label":"Fiber / communications","value":null,"unit":null,"display":null,"evidence_class":"UNKNOWN","confidence":"UNKNOWN","support":"unverified","review":"CHECKED","source_ids":[],"source_urls":[],"checked":null,"observed_date":null,"effective_date":null,"methodology":null,"notes":"No public carrier or route disclosure located. Route: UNKNOWN."},{"value_id":"hut8-beacon-point:relationship:transportation_road_access","facility_id":"hut8-beacon-point","group":"relationship","attribute":"transportation_road_access","label":"Road access","value":"FM 1694","unit":null,"display":null,"evidence_class":"VERIFIED","confidence":"MODERATE","support":"filed","review":"CHECKED","source_ids":["tdlr-tabs","connectcre-tdlr"],"source_urls":["https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611","https://www.connectcre.com/stories/data-center-operator-to-begin-work-on-399m-corpus-christi-campus/"],"checked":"2026-10-28","observed_date":null,"effective_date":null,"methodology":null,"notes":"Filed address is on FM 1694. Gate locations and emergency access routes are UNKNOWN. Route: LOGICAL_ONLY."}],"sources":[{"source_id":"caller-times-nueces-address-2026-10-02","title":"Nueces County address covers finances, data centers, 1914 courthouse","publisher":"Corpus Christi Caller-Times (republished by AOL)","url":"https://www.aol.com/articles/nueces-county-address-covers-finances-153610000.html","kind":"LOCAL_REPORTING","primary":false,"published_date":"2026-10-02","accessed_date":"2026-11-14","added_date":"2026-10-03","retrieval":"DIRECT"},{"source_id":"coastal-bend-current-oversight","title":"Beacon Point moves ahead with no local oversight","publisher":"Coastal Bend Current","url":"https://www.coastalbendcurrent.com/blogs/beacon-point-moves-ahead-without-any-local-oversight","kind":"LOCAL_REPORTING","primary":false,"published_date":null,"accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"connectcre-tdlr","title":"Data Center Operator to Begin Work on $399M Corpus Christi Campus","publisher":"Connect CRE","url":"https://www.connectcre.com/stories/data-center-operator-to-begin-work-on-399m-corpus-christi-campus/","kind":"TRADE_REPORTING","primary":false,"published_date":null,"accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"constructionfront-financing","title":"Hut 8 Closes US$4.25 Billion Construction Financing for Beacon Point Data Center in Texas","publisher":"Construction Front","url":"https://constructionfront.com/2026-06-12-hut-8-closes-us4-25-billion-construction-financing-for-beacon-point-data-center-in-texas/","kind":"TRADE_REPORTING","primary":false,"published_date":"2026-06-12","accessed_date":"2026-11-14","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"eia-860m-2026-08","title":"Preliminary Monthly Electric Generator Inventory (EIA-860M), August 2026","publisher":"U.S. Energy Information Administration","url":"https://www.eia.gov/electricity/data/eia860m/xls/august_generator2026.xlsx","kind":"GOVERNMENT_DATASET","primary":true,"published_date":"2026-09-23","accessed_date":"2026-10-12","added_date":"2026-10-12","retrieval":"DIRECT"},{"source_id":"enr-jacobs-beacon-point","title":"Jacobs Expands EPCM Role With Hut 8's 1-GW Texas AI Campus","publisher":"Engineering News-Record","url":"https://www.enr.com/articles/63004-jacobs-expands-epcm-role-with-hut-8s-1-gw-texas-ai-campus","kind":"TRADE_REPORTING","primary":false,"published_date":"2026-05-15","accessed_date":"2026-11-14","added_date":"2026-10-12","retrieval":"DIRECT"},{"source_id":"epa-frs-beacon-point","title":"Facility Registry Service detail report, registry ID 110072227954 (Beacon Point Data Center Project)","publisher":"U.S. Environmental Protection Agency (Facility Registry Service)","url":"https://frs-public.epa.gov/ords/frs_public2/fii_query_dtl.disp_program_facility?p_registry_id=110072227954","kind":"GOVERNMENT_DATASET","primary":false,"published_date":null,"accessed_date":"2026-11-02","added_date":"2026-11-02","retrieval":"DIRECT"},{"source_id":"ercot-eir-25rpg016","title":"ERCOT Independent Review of STEC Nueces Green Ammonia Load Interconnection Project (25RPG016), Board item 5.2","publisher":"Electric Reliability Council of Texas (ERCOT)","url":"https://www.ercot.com/files/docs/2026/04/13/5.2-25RPG016-STEC-Nueces-Green-Ammonia-Load-Interconnection-Project.pdf","kind":"REGULATORY_RECORD","primary":true,"published_date":"2026-04-13","accessed_date":"2026-11-14","added_date":"2026-10-12","retrieval":"DIRECT"},{"source_id":"ercot-tpit-2026-07","title":"Transmission Project and Information Tracking (TPIT), July 2026 ad hoc update","publisher":"Electric Reliability Council of Texas (ERCOT)","url":"https://www.ercot.com/files/docs/2022/03/02/ERCOT-July-Ad-Hoc-TPIT-No-Cost-071326-UPDATE.xlsx","kind":"REGULATORY_RECORD","primary":true,"published_date":"2026-07-17","accessed_date":"2026-10-12","added_date":"2026-10-12","retrieval":"DIRECT"},{"source_id":"hut8-8k-notes-2026-06","title":"Hut 8 Announces Pricing of $4.25 Billion of Investment-Grade Senior Secured Notes for Beacon Point Data Center Project (Form 8-K, Ex. 99.1)","publisher":"Hut 8 Corp. (SEC EDGAR)","url":"https://www.sec.gov/Archives/edgar/data/1964789/000110465926070744/tm2616926d1_ex99-1.htm","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":"2026-06-04","accessed_date":"2026-11-02","added_date":"2026-11-02","retrieval":"DIRECT"},{"source_id":"hut8-pr-phase1","title":"Hut 8 Commercializes First Phase of 1 GW Beacon Point AI Data Center Campus with 15-Year, 352 MW IT Lease with Base-Term Contract Value of $9.8 Billion","publisher":"Hut 8 Corp. (via PR Newswire)","url":"https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":"2026-05-06","accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"hut8-pr-phase2","title":"Hut 8 Fully Commercializes 1 GW Beacon Point AI Data Center Campus with Second 352 MW IT Lease, Bringing Campus-Level Base-Term Contract Value to $19.6 Billion","publisher":"Hut 8 Corp. (via PR Newswire)","url":"https://www.prnewswire.com/news-releases/hut-8-fully-commercializes-1-gw-beacon-point-ai-data-center-campus-with-second-352-mw-it-lease-bringing-campus-level-base-term-contract-value-to-19-6-billion-302829514.html","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":"2026-07-20","accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"hut8-pr-responsible","title":"Hut 8 Affirms Commitment to Responsible Data Center Development Following Directive from Texas Governor Greg Abbott","publisher":"Hut 8 Corp. (via PR Newswire)","url":"https://www.prnewswire.com/news-releases/hut-8-affirms-commitment-to-responsible-data-center-development-following-directive-from-texas-governor-greg-abbott-302847136.html","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":"2026-08-10","accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"hut8-q2-2026","title":"Hut 8 Reports Second Quarter 2026 Results (Form 8-K, Ex. 99.1)","publisher":"Hut 8 Corp. (SEC EDGAR)","url":"https://www.sec.gov/Archives/edgar/data/1964789/000110465926090041/tm2621890d1_ex99-1.htm","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":"2026-08-04","accessed_date":"2026-11-02","added_date":"2026-11-02","retrieval":"DIRECT"},{"source_id":"hut8-site","title":"Beacon Point | Hut 8","publisher":"Hut 8 Corp.","url":"https://www.hut8.com/data-centers/beacon-point","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":null,"accessed_date":"2026-11-14","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"kristv-beacon-point","title":"Beacon Point AI: Massive data center planned for Nueces County","publisher":"KRIS 6 News","url":"https://www.kristv.com/news/local-news/in-your-neighborhood/corpus-christi/calallen/beacon-point-ai-massive-data-center-planned-for-nueces-county","kind":"LOCAL_REPORTING","primary":false,"published_date":null,"accessed_date":"2026-11-14","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"ncesd1-clack-email-2026-10-06","title":"Email from Chief Michael Clack (Annaville Fire Department, Nueces County ESD #1) on Beacon Point fire response","publisher":"Nueces County Emergency Services District #1 (Annaville Fire Department)","url":null,"kind":"CORRESPONDENCE","primary":true,"published_date":"2026-10-06","accessed_date":"2026-10-06","added_date":"2026-10-07","retrieval":"DIRECT"},{"source_id":"ncesd1-clack-email-2026-10-07","title":"Follow-up email from Chief Michael Clack (Annaville Fire Department, Nueces County ESD #1) on Beacon Point cost recovery and site-plan meetings","publisher":"Nueces County Emergency Services District #1 (Annaville Fire Department)","url":null,"kind":"CORRESPONDENCE","primary":true,"published_date":"2026-10-07","accessed_date":"2026-10-07","added_date":"2026-10-07","retrieval":"DIRECT"},{"source_id":"needham-ercot-review","title":"Hut 8 says Beacon Point may be among 23 Texas projects cleared for review: Needham","publisher":"Yahoo Finance","url":"https://finance.yahoo.com/technology/ai/articles/hut-8-says-beacon-point-132234125.html","kind":"TRADE_REPORTING","primary":false,"published_date":null,"accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"nueces-pusley-email-2026-09-25","title":"Email from Commissioner Mike Pusley (Nueces County, Precinct 1) on Beacon Point water and county authority","publisher":"Nueces County Commissioners Court, Precinct 1","url":null,"kind":"CORRESPONDENCE","primary":true,"published_date":"2026-09-25","accessed_date":"2026-09-26","added_date":"2026-09-26","retrieval":"DIRECT"},{"source_id":"nws-crp-wind","title":"NWS Corpus Christi Local Research: Wind Study","publisher":"National Weather Service, Corpus Christi (CRP)","url":"https://www.weather.gov/crp/localresearch-windstudy","kind":"GOVERNMENT_PAGE","primary":true,"published_date":null,"accessed_date":"2026-09-23","added_date":"2026-09-23","retrieval":"SEARCH_EXCERPT"},{"source_id":"puct-55999-victoria-warburton","title":"ERCOT RPG acceptance, AEPSC Victoria to Warburton 138-kV Line Rebuild Project (PUCT Project No. 55999, Item 153)","publisher":"ERCOT and AEP Service Corporation, filed at the PUCT","url":"https://interchange.puc.texas.gov/Documents/55999_153_1527650.PDF","kind":"REGULATORY_RECORD","primary":true,"published_date":"2025-08-05","accessed_date":"2026-11-02","added_date":"2026-11-02","retrieval":"DIRECT"},{"source_id":"rtfc-site","title":"Welcome to Refinery Terminal Fire Company","publisher":"Refinery Terminal Fire Company","url":"https://www.rtfc.org/","kind":"ORGANIZATION_PAGE","primary":true,"published_date":null,"accessed_date":"2026-11-14","added_date":"2026-10-07","retrieval":"DIRECT"},{"source_id":"tdlr-tabs","title":"Texas Architectural Barriers (TABS) project registration: Beacon Point, 4650 FM 1694, Robstown","publisher":"Texas Department of Licensing and Regulation","url":"https://www.tdlr.texas.gov/TABS/Search/Print/TABS2027000611","kind":"REGULATORY_RECORD","primary":true,"published_date":null,"accessed_date":"2026-10-28","added_date":"2026-09-23","retrieval":"DIRECT"},{"source_id":"tx-cc-planning-commission-2026-06-10","title":"City of Corpus Christi Planning Commission agenda packet, June 10, 2026: PL9308, Final Plat – Farias Tracts, Lots 1 & 2, Block 1","publisher":"City of Corpus Christi, Planning Commission","url":"https://corpuschristi.legistar.com/View.ashx?GUID=6D18E532-537E-4AD5-8948-D1FE1623A5C3&ID=1416930&M=PA","kind":"GOVERNMENT_PAGE","primary":true,"published_date":"2026-06-10","accessed_date":"2026-11-15","added_date":"2026-11-15","retrieval":"DIRECT"},{"source_id":"tx-hut8-q3-2026","title":"Hut 8 Reports Third Quarter 2026 Results","publisher":"Hut 8 Corp.","url":"https://www.hut8.com/news-insights/press-releases/hut-8-reports-third-quarter-2026-results","kind":"COMPANY_DISCLOSURE","primary":true,"published_date":"2026-11-04","accessed_date":"2026-11-14","added_date":"2026-11-14","retrieval":"DIRECT"},{"source_id":"tx-nueces-cc-agenda-2026-05-13","title":"Nueces County Commissioners Court agenda item, May 13, 2026: Beacon Point Data Center Reinvestment Zone","publisher":"Nueces County Commissioners Court","url":"https://public.destinyhosted.com/agenda_publish.cfm?id=68323&mt=ALL&get_month=5&get_year=2026&dsp=ag&seq=918","kind":"GOVERNMENT_PAGE","primary":true,"published_date":null,"accessed_date":"2026-11-15","added_date":"2026-11-15","retrieval":"DIRECT"},{"source_id":"tx-nueces-cc-agenda-2026-11-18","title":"Nueces County Commissioners Court agenda, regular meeting, November 18, 2026","publisher":"Nueces County Commissioners Court","url":"https://public.destinyhosted.com/agenda_publish.cfm?id=68323&mt=ALL&get_month=11&get_year=2026&dsp=ag&seq=934","kind":"GOVERNMENT_PAGE","primary":true,"published_date":null,"accessed_date":"2026-11-15","added_date":"2026-11-15","retrieval":"DIRECT"}],"changes":[{"date":"2026-11-15","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Added a \"Who does what?\" reference: the city, county, emergency, environmental, electricity, and project organizations around the campus, what each can decide, and where to ask for records. New records: city staff reviewed and recommended approval of a final plat naming Beacon Point DC LLC as owner (June 10, 2026 packet; the vote and recording are not verified), and the county listed a closed-session item on a proposed Beacon Point reinvestment zone on May 13, 2026.","attribute":null,"previous":null,"source_ids":["tx-cc-planning-commission-2026-06-10","tx-nueces-cc-agenda-2026-05-13","tx-nueces-cc-agenda-2026-11-18"]},{"date":"2026-11-14","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Company reports substation and Phase 1 foundation/underground utility work, with initial data-hall delivery targeted for Q3 2027 (Phase 1) and Q2 2028 (Phase 2).","attribute":null,"previous":null,"source_ids":["tx-hut8-q3-2026"]},{"date":"2026-11-02","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Hut 8's SEC filings now confirm the campus substation is under construction on the site (previously a trade report only); its owner and voltage remain unpublished. Added the site's stormwater construction authorization and an ERCOT-accepted study of the Lon Hill area that modeled a code-named 1,000 MW load not linked to Beacon Point by any source.","attribute":"substation_construction","previous":null,"source_ids":["hut8-q2-2026","hut8-8k-notes-2026-06","epa-frs-beacon-point","puct-55999-victoria-warburton"]},{"date":"2026-10-28","facility_id":"hut8-beacon-point","kind":"CORRECTION","summary":"Removed the sourced prevailing-wind default: the cited NWS page studies selected severe-wind events and does not establish prevailing wind climatology. Local prevailing wind is UNKNOWN; scenario wind remains an illustrative input.","attribute":"wind_climatology","previous":"135 degrees; NWS Corpus Christi prevailing SE","source_ids":["nws-crp-wind"]},{"date":"2026-10-12","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Recorded that the first 352 MW IT lease requires about 500 MW of utility capacity, and that Hut 8's release names AEP Texas as the party to the 1,000 MW interconnection agreement.","attribute":"phase1_utility_capacity","previous":null,"source_ids":["hut8-pr-phase1"]},{"date":"2026-10-12","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Hut 8's project page says the company pre-funded the infrastructure costs required to serve its load; a trade report says substation construction has commenced. The amount paid and the substation's location remain unknown.","attribute":"grid_infrastructure_funding","previous":null,"source_ids":["hut8-site","enr-jacobs-beacon-point"]},{"date":"2026-10-12","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Added area grid context: ERCOT's April 2026 review found that a separate 1,150 MW load in Nueces County requires transmission upgrades. The county's existing supply capacity is not published, and ERCOT's project list does not name the station serving Beacon Point. Recorded the generating capacity located in the county: about 3,040 MW net summer.","attribute":"area_transmission_study","previous":null,"source_ids":["ercot-eir-25rpg016","ercot-tpit-2026-07","eia-860m-2026-08"]},{"date":"2026-10-07","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"In a follow-up, the ESD #1 chief wrote that cost recovery for an extended response has not been discussed (the district typically charges only for hazmat responses) and that the district has attended a multi-agency site-plan meeting for the construction phases, with more planned.","attribute":"extended_response_cost_recovery","previous":null,"source_ids":["ncesd1-clack-email-2026-10-07"]},{"date":"2026-10-06","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"The Nueces County ESD #1 (Annaville) fire chief wrote that the district has fire jurisdiction of the area while the City of Corpus Christi Fire Marshal's Office reviews the fire code, including fire flow.","attribute":"fire_jurisdiction","previous":"Primary fire jurisdiction UNKNOWN","source_ids":["ncesd1-clack-email-2026-10-06"]},{"date":"2026-10-06","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"The chief reported battery-fire training for responding crews, a pre-plan covering reignition monitoring, and mutual aid with the Corpus Christi Fire Department and the Refinery Terminal Fire Company (RTFC); runoff containment has not been addressed yet.","attribute":"mutual_aid","previous":null,"source_ids":["ncesd1-clack-email-2026-10-06"]},{"date":"2026-10-03","facility_id":"hut8-beacon-point","kind":"STATUS_CHANGE","summary":"Corrected the stage to under construction: Hut 8's July release says construction had commenced.","attribute":"status","previous":"Under development · fully leased; PERMITTING","source_ids":["hut8-pr-phase2"]},{"date":"2026-10-03","facility_id":"hut8-beacon-point","kind":"NEW_INFO","summary":"Commissioner Pusley said the county declined to offer Hut 8 a tax abatement; no formal decision record was located.","attribute":"county_tax_abatement","previous":null,"source_ids":["caller-times-nueces-address-2026-10-02"]},{"date":"2026-10-03","facility_id":"hut8-beacon-point","kind":"CORRECTION","summary":"Hut 8's representative reported on-site backup generation for the project; installation, type, fuel, and capacity remain unknown.","attribute":"backup_generation","previous":"Backup generation (type, fuel, capacity) UNKNOWN","source_ids":["kristv-beacon-point"]},{"date":"2026-09-23","facility_id":"hut8-beacon-point","kind":"ADDED","summary":"Added to the atlas.","attribute":null,"previous":null,"source_ids":[]}],"grid_projects":[],"cost_allocation":[{"allocation_id":"hut8-beacon-point:tx-bp-prefunded-connection","facility_id":"hut8-beacon-point","subject":"connection","payer":"FACILITY","mechanism":"The company says it pre-funded the infrastructure costs required to serve its load; a trade report calls the payment a contribution in aid of construction.","amount_usd":null,"basis":"Company statement","evidence_class":"VERIFIED","confidence":"MODERATE","source_ids":["hut8-site","enr-jacobs-beacon-point"],"source_urls":["https://www.hut8.com/data-centers/beacon-point","https://www.enr.com/articles/63004-jacobs-expands-epcm-role-with-hut-8s-1-gw-texas-ai-campus"],"notes":"The company's account. No AEP Texas, ERCOT, or Public Utility Commission record of the payment was located, and the amount and what it covers are not published."}]}